A manager wishes to build three control limits for a process. The goal value for the mean of the process is ten units, and the standard deviation of the process is 6. If samples of size 9 are to be taken, the UCL and LCL will be
12 and 8
8 and 12
-8 and 28
16 and 4
4 and 16