a. In month 9 the following project information is available: actual cost is $2,000, earned value is $2,100, and planned cost is $2,400. Compute the Schedule Variance and Cost Variance for the project.

b. On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the Schedule Variance, Cost Variance, and Cost Performance Index for the project. What is your assessment of the project on day 51?

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M92179803

Have any Question?


Related Questions in Operation Management

Information security professionals are sometimes involved

Information security professionals are sometimes involved in communications that are confidential. These communications might be a component of a criminal investigation or a policy violation within the organization. It m ...

Discussion minimum 1 page is required please do not attempt

Discussion: (Minimum 1 page is required) (Please do not attempt to solve if you can not fulfill the requirement) Major threats facing the Vitamin Shoppe, and reflect on how these might be eliminated, diminished, or defle ...

Assignment social media marketing plan part ayou are

Assignment : Social Media Marketing Plan: Part A You are required to submit a social media marketing plan for a hypothetical product or service based company (the business cannot be a real business). You will build this ...

Smartbeans is canadarsquos largest online retailer of

SmartBeans is Canada’s largest online retailer of fair-trade organic coffee, and imports coffee beans from several countries. SmartBeans operates 300 days a year and sells an average of 150 pounds of Harar (Ethiopia) Fai ...

1 how might a swot strengths weaknesses opportunities and

1. How might a SWOT (strengths, weaknesses, opportunities, and threats) analysis be of use for identifying measures in a balanced scorecard? What; of questions might you as 2. What is the market potential for candy? 3. D ...

1 in what stage of the its life cycle is social media

1. In what stage of the its life cycle is social media? Support your answer. 2. Write case study about problem happened in oil refinery? 3. Discuss speed as the newest competitive advantage and its value.

1 some organizations have the mantra ldquoinnovate or

1. Some organizations have the mantra “innovate or die.” Do you believe this is true for the average organization? When is innovation important and when is it not? 2. Juanita gathers her employees to solicit their opinio ...

Now that you have identified the business problem and

Now that you have identified the business problem and translated it into an analytics problem, you can now identify the data needs and acquire the data. Provide a 500-1,000 word paper that, at a minimum, identifies the d ...

Assignmentchoosing the right mentor is critical to ones

Assignment Choosing the "right" mentor is critical to one's long term success in life. Mentors assist us in determining what it takes to be successful in one's chosen vocation, academic program, or in reaching a short or ...

Robin attended a high school baseball game at the local

Robin attended a high school baseball game at the local high school baseball field. The field had fencing 24 feet high and 50 feet wide behind home plate. The 24 foot high fencing was located in front of bleachers for sp ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As