A given activity was budgeted to cost $35,000 and consume 10 days. One crew is assigned to the task at a budget of $3500 per day. After 3 days the job is determined to be 40 percent complete. To date, $15,500 has been paid out on the activity. What are the schedule and cost variances and indices? Provide a summary of the status of the activity.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M91765888

Have any Question?


Related Questions in Operation Management

Suppose jones company has orders from three customers

Suppose Jones Company has orders from three customers located in the same market area. One order has a total weight of 3,600 pounds, the second weighs 8,300 pounds, and the third weighs 12,100 pounds. The transportation ...

1 use the drag and drop function to put the following

1. Use the Drag and Drop function to put the following events in the order they occur in the Amazon product receiving and order fulfillment process: Put the item in a bin/tote. Once the item is in its bin in its specific ...

In regards to the namibian justice system1 briefly discuss

In regards to the Namibian justice system 1. Briefly discuss factors affecting contractual capacity 2. Briefly discuss the different forms of breach of contract 3. Briefly discuss how a contract can be terminated Answer ...

1 answer the following question in 250 words make a list of

1. Answer the following question in 250 words: Make a list of all the countries where the Nissan Leaf is available. How have marketers adapted the product to suit these markets? 2. What is 'vampire effect' in marketing? ...

1 what is quantitative research and how is it useful2 how

1) What is quantitative research and how is it useful? 2) How does it differ from qualitative research? 3) Describe an idea you have for a quantitative research project and explain why this approach would be best.

1 what are the current challenges in managing people and

1. What are the current challenges in managing people and how can HRM help managers overcome these problems? 2. Explain XPO Logistics Inc. supply chain operations. 3. Personally, if you were a Human Resource Manager, wha ...

This analysis paper involves a case analysis you must

This analysis paper involves a case analysis. You must first choose the case you wish to analyze. You can find the cases on our Canvas site, in the Assignments section. You'll see a folder that contains several cases fro ...

Zaras stategy execution capabilitieszara a major division

Zara's Stategy Execution Capabilities. Zara, a major division of Inditex Group, is a leading "fast fashion" retailer. As soon as designs are seen in high-end fashion houses such as Prada, Zara's design team sets to work ...

The plant managers of abc corporations five plants have met

The plant managers of ABC Corporation's five plants have met at a common location at 8:00 am every Monday morning for 20 years. The people serving as plant managers have changed several times during this period, but the ...

1 product placement decreases realism in programming which

1. Product placement decreases realism in programming, which is why producers rarely want to use them. Select one: True False 2. One disadvantage of consumer generated advertising is that consumer’s often resent being as ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As