The following is a table of activities associated with a project at Bill Figg Enterprises, their durations and what activities each must precede:
Activity Duration (weeks) Precedes
A (start) 1 B, C
B 1 E
C 4 F
E 2 F
F (end) 2 _
a Draw an AON diagram of the project including activity durations and define the critical path, lisitng all critical activities in chronological order and list the project duration (in weeks)?