The forecast requirements for an electric hand drill for the next 6 weeks are 15,40,10,20,50,and 30 units. The marketing department has booked orders totalling 20, 25, 10 and 20 units for delivery in the first (current), second, and third, and fourth week. Currently, 30 hand drills are in stock. The policy to order in lots of 60 units. Lead time is one week.
A. develop the MPS record for the hand drills
B. A distributor of the hand drills places an order for 15 units. What is the appropriate shipping date for the entire order?