A contracting company has been awarded a contract for converting 10 miles of a high-traffic gravel road into a hot-mixed asphalt pavement. The contract includes the tasks of reshaping and leveling the original road. A major part of the project is to be executed during nights and under cold weather conditions.
Briefly discuss the sequence of construction for this project, including the rolling sequence for the hot-mixed asphalt pavement portion of the project. Explain why cold-mixed pavement construction might have been considered unsuitable for this project.