a. A machine shop needs to schedule jobs to be processed.  Sequence the jobs using the following rules: FCFS, SPT, and EDD.  (Assume the list is by order of arrival.)  For each rule, determine the average job flow time, the average tardiness, and the average number of jobs at the work center.

Job

Job time

(hours)

Due Date

(hours from now)
A 7 21
B 10 12
C 3 8
D 9 20
E 15 18

Type your response in the text box below.  

You MUST show your work, either in the box below, or as an attachment.  Your choice.

You may copy and past the template below to show your final answers.  Use bold text to indicate the best method for each metric.

  FCFS

(5 points)
SPT

(5 points)
EDD

(5 points)
CR

(6 points)
Job Sequence        
Average job flow time        
Average tardiness        
Average number of jobs at work center        

Which scheduling rule would you recommend and why?  (4 points)

B. Peter Pepperoni, owner of the Perfect Pasta Pizza Parlor, uses 25 pounds of pepperoni each day in preparing pizzas. Order costs for pepperoni are $10.00 per order, and carrying costs are 5 cents per pound per day. Lead time for each order is 3 days.  Currently, he orders 80 pounds of pepperoni at a time.

a. At what point (inventory level) should he reorder pepperoni?  (5 points)

b. What would be the length of an order cycle (in days)?  (5 points)

c. What is the average inventory level?  (5 points)

d. What is the total daily cost of inventory?  (5 points)

e. What is the economic order quantity for pepperoni?  (5 points)

f. If he changes to the economic order quantity, what would be the new daily inventory costs?  (5 points)

Type your response in the text box below.  

Please use bold text to make your final answer for each part stand out more clearly.

You MUST show your work, either in the box below, or as an attachment.  Your choice.

c. A manager must assign four engineers to projects, one to a project.

  A B C D
Engineer 1 17 11 19 18
Engineer 2 16 17 11 9
Engineer 3 24 27 16 13
Engineer 4 27 17 23 24

a. Given the cost figures below for each project-engineer combination, determine assignments such that total cost will be minimized.  (10 points)

b. The leader of Project C has indicated that he does not want engineer 2 or 3 on his project. Rework the assignment problem, keeping in mind that two combinations are undesirable, such that total cost will be minimized.  (15 points)

Type your response in the text box below.  

You MUST show your work, either in the box below, or as an attachment.  Your choice.
You may copy and past the template below to show your final answers.

Engr 1: xx

Engr 2: xx

Engr 3: xx

Engr 4: xx

Cost: xx

d.

Given the following data for a make or buy decision:

Alternative Fixed Cost Variable Cost
Buy $0 per year $8 per unit
Make $100,000 per year $4 per unit

a. What is the total cost to buy a quantity of 15,000 units per year?  (2.5 points)

b. What is the total cost to make a quantity of 15,000 units per year?  (2.5 points)

c. For what quantity would you be indifferent between buying or making?  (2.5 points)

d. Which alternative would you select for a quantity of 24,000 units per year?  (2.5 points)

e. What alternative is preferred for 32,000 units per year, and what is the cost?  (5 points)

f. What would be your cost savings for the preferred alternative, for 32,000 units per year, compared to the other alternative?  (5 points)

Type your response in the text box below.  

Please use bold text to make your final answer for each part stand out more clearly.

This  is the answer done by myself, please don't buy the answer, the answer is wrong.

  FCFS

(5 points)
SPT

(5 points)
EDD

(5 points)
CR

(6 points)
Job Sequence  A-B-C-D-E  C-A-D-B-E  C-B-E-D-A  E-D-C-A-B
Average job flow time  23.40  21.00  25.00   28.8
Average tardiness   10.4     8.60     10.20    13.6
Average number of jobs at work center  2.65    2.39     2.84    3.44



Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M91275788
  • Price:- $30

Guranteed 24 Hours Delivery, In Price:- $30

Have any Question?


Related Questions in Operation Management

Human resource information managementwhat is the difference

Human Resource Information Management; What is the difference between synchronous and asynchronous training format? What are the key benefits of Web technology in managing the content of knowledge management systems? Wha ...

1 tell me about a hypothesis that you would like to test

1. Tell me about a hypothesis that you would like to test that relates to marketing/consumer behavior. What is the null hypothesis? What is the alternative hypothesis? 2. Explain the principle of unjust enrichment. 3. Pr ...

Vending machine operator suffers the cost of a product

Vending Machine operator suffers the cost of a product recall. Is the wholesaler responsible if the manufacturer is unable to pay for all the costs of a recall? If the manufacturer or wholesaler must pay for the legitima ...

Answer the following question what are some of the

Answer the following Question : What are some of the components of these cultures that you need to understand from a business standpoint? How are they different in each country? Specifically, what considerations will be ...

Students are going through a three-step process to obtain

Students are going through a three-step process to obtain their ID cards. Each student will spend 2 minutes at registration desk before going to one of three cashiers to pay a fee for the ID card. After that, he/she will ...

You open a new clothing store in beautiful southern

You open a new clothing store in beautiful Southern California, near the beach. The clothing is designed and marketed to young, athletic, attractive people (or at least people who aspire to be young, athletic, and attrac ...

You are the contracting officer for an air-to-ground

You are the contracting officer for an air-to-ground missile development program. A contract for pre-production models of the missile was awarded by your predecessor and the contractor is behind schedule. In a program me ...

1 discuss the three methods for choosing an arbitrator2

1. Discuss the three methods for choosing an arbitrator. 2. What are the possible positions concerning individual rights under collective bargaining agreements. (Please list all of them in your answer.) 3. Describe how D ...

Bertha takes her roommatersquos credit card with the intent

Bertha takes her roommate’s credit card with the intent to charge for expenses she will incur on a vacation. Bertha’s first stop is at the Shell gas station where she used the card to fill her car with gas. • Discuss whe ...

1 suppose the holding cost for each maple desk is 5 per day

1. Suppose the holding cost for each maple desk is $5 per day. Also, every maple desk that is backordered cost Bomberland $20 per day. What is the approximate in-stock probability? (Hint: Treat this question as a newsven ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As