1.Which of the following is NOT considered to be a characteristic of a project?

A)An established objective

B)A clear beginning and end

C)Specific time, cost and performance requirements

D)For internal use only

E)Something never been done before

2.When considering the following activities, which is the best example of a project?

A)Processing insurance claims

B)Producing automobiles

C)Writing a policy manual

D)Monitoring product quality

E)Overseeing customer requests

3.In the _____________ stage of the project life cycle, project objectives are established, teams are formed, and major responsibilities are assigned.

A)Identifying

B)Defining

C)Planning

D)Executing

E)Closing

4.In the _____________ stage of the project life cycle, a major portion of the physical project work performed.

A)Identifying

B)Defining

C)Planning

D)Executing

E)Closing

5.Which of the following is NOT typical of a project manager?

A)Managing a temporary activity

B)Overseeing existing operations

C)Managing a non-repetitive activity

D)Responsible for time, cost and performance trade-offs

E)Work with a group of outsiders, including vendors and suppliers

6.Which of the following choices is NOT one of the driving forces behind the increasing demand for project management?

A)Compression of the product life cycle

B)Knowledge explosion

C)Increasing need for multi-project management

D)Declining need for product customization

E)More sustainable business practices

7.Which dimension of project management centers on creating a temporary social system within a larger organizational environment that combines the talents of a divergent set of professionals working to complete the project?

A)Communication

B)Sociocultural

C)Social

D)Technical

E)Scheduling

8.Which of the following statements is true?

A)Project management is far from a standard way of doing business

B)Project management is increasingly contributing to achieving organizational strategies

C)Project management is being used at a consistent percentage of a firm's efforts

D)Project management is a specialty that few organizations have access to

E)All of these statements are false

9.Project management is important to understand when someone is a part of a project team because they

A)Work with others to create a schedule and budget

B)Need to understand project priorities so they can make independent decisions

C)Need to be able to monitor and report project progress

D)Need to understand the project charter or scope statement that defines the objectives and parameters of the project

E)All of these are reasons it is important for project team members to understand project management

10.Which of these is NOT part of the "technical dimension" of project management?

A)WBS

B)Budgets

C)Problem solving

D)Schedules

E)Status reports

11.Corporate downsizing has increased the trend toward

A)Reducing the number of projects a company initiates

B)Outsourcing significant segments of project work

C)Using dedicated project teams

D)Shorter project lead times

E)Longer project lead times

12.The following is NOT true about project management

A)It is not limited to the private sector

B)Many opportunities are available for individuals interested in this career path

C)It improves one's ability to plan, implement and manage activities to accomplish specific organizational objectives

D)It focuses primarily on technical processes

E)It is a set of tools

13.Governance of all project management processes and procedures helps provide senior management with all of the following EXCEPT

A)A method to ensure projects that are important to senior management are being implemented

B)An assessment of the risk their portfolio of projects represents

C)An overview of all project management activities

D)A metric to measure the improvement of managing projects relative to others in the industry

E)A big picture of how organizational resources are being used.

14.Which of the following is a good example of a program?

A)Planting a garden

B)Developing a new residential area that includes six custom homes

C)Developing a new marketing plan

D)Taking notes each class meeting to prepare for the final

E)Planning a wedding

15.Which of the following represents the correct order of stages within the project life cycle

A)Planning, Defining, Executing, Closing

B)Closing, Planning, Defining, Executing

C)Defining, Planning, Executing, Closing

D)Executing, Defining, Planning, Closing

E)Planning, Defining, Closing, Executing

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M92192417
  • Price:- $15

Priced at Now at $15, Verified Solution

Have any Question?


Related Questions in Operation Management

Conflictdefine functional versus dysfunctional conflict in

Conflict Define functional versus dysfunctional conflict in a work group and explain how you can increase functional conflict and decrease dysfunctional conflict. Develop a response that includes examples and evidence to ...

For this assignment you will need to find 2 articles in

For this assignment, you will need to find 2 articles in business that can help describe what are IT strategic initiative being undertaken by an organization are like. Choose a different organization for each of the arti ...

Coping with problems joe is a little nervous he has just

Coping With Problems Joe is a little nervous. He has just been transferred from another plant to take over a production line. Production is down and there is a serious problem with absenteeism. To make matters worse, the ...

Over 30 years ago michael porter identified a holistic

Over 30 years ago Michael Porter identified a holistic approach to understanding how competitive forces shape strategy. He posited that the only way to truly insulate an organization from underlying economic volatility i ...

You are the contracting officer for an air-to-ground

You are the contracting officer for an air-to-ground missile development program. A contract for pre-production models of the missile was awarded by your predecessor and the contractor is behind schedule. In a program me ...

The ikea case provides an excellent opportunity to apply

The IKEA case provides an excellent opportunity to apply strategic management concepts to a large privately-held company that is expanding into India. IKEA is a Netherlands-based Swedish company with a presence in 44 cou ...

Can you answer for me the following questions about social

Can you answer for me the following questions about social loafing and the three main causes of free-riding. 1. Give a description of the phenomenon of social loafing. 2. Give a description of the phenomenon of free-ridi ...

1 analyzing the bridgestonefirestone and ford motor company

1. Analyzing the Bridgestone/Firestone and Ford motor company, is it sufficient to use the ISO/QS 9000 standards as the main basis of vendor/product selection? 2. What position to these cars company ( 1. Volkswagen, 2. F ...

Research the effect of primary and secondary seat belt laws

Research the effect of primary and secondary seat belt laws on the occurrence of motor-vehicle injuries and fatalities. Explain how epidemiologic studies influenced the development of current seat belt laws. Describe how ...

Please provide a brief paragrap of the key takaways from

Please provide a brief paragrap of the key takaways from each of the following topics: Designing Clear Visuals in business reports Designing Successful Documents and Websites Writing Winning Proposals

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As