1.The process of forecasting or approximating the time and cost of completing project deliverables is called

A) Budgeting

B) Predicting

C) Estimating

D) Planning

E) Guesstimating

2.Janet is forecasting how much money her department needs to support a new project. She estimates that two people and $25,000 in expenses will cover her needs. Because management typically insists on reducing forecasts by 20 percent, she increases her estimates to allow for that reduction. Which of the following factors is illustrated in this situation?

A) Padding estimates

B) Planning horizon

C) Project structure

D) People

E) Organization culture

3.Top-down estimates are most likely to occur during the ______ phase.

A) Concept

B) Planning

C) Execution

D) Delivery

E) All of these are equally likely

4.Sean is forecasting the time and cost of developing a customized software program by looking at the number of inputs, outputs, inquires, files, and interfaces. Which of the following methods is he using?

A) Ratio

B) Template

C) Apportion

D) Function point

E) Learning curve

5.Learning curves are more likely to apply in situations where most of the costs are

A) Materials

B) Labor

C) Overhead

D) Evenly spread over materials, labor, and overhead

E) All of these are equally likely situations for learning curves

6.The approach that begins with a top-down estimate for the project and then refines estimates as the project is implemented is known as ______ method.

A) Function point

B) Template

C) Learning curve

D) Phase estimating

E) Apportion

7.The accuracy of top-down estimates will typically be in the range of

A) Minus 50% to plus 50%

B) Minus 0% to plus 75%

C) Minus 20% to plus 60%

D) Minus 35% to plus 35%

E) Minus 10% to plus 30%

8.The cost to prepare bottom-up estimates will typically run how much more than the costs to prepare the top-down estimates?

A) About the same

B) About twice as much

C) About three times as much

D) About four times as much

E) About five times as much

9.Project costs are typically viewed from all of the following except:

A) Scheduled

B) Sunk

C) Actual

D) Committed

E) All of these are correct

10.Which of the following is not one of the recommended guidelines for developing useful work package estimates?

A) Estimates should be made by those responsible for the work

B) Use several people to estimate the same work

C) Estimates should be based on normal conditions

D) Estimates should include a normal level of contingency

E) Estimates should be independent of other projects

11. Reasons why estimating time and cost are important include all of the following except:

A) To schedule work

B) To determine how long the project should take and cost

C) To develop cash flow needs

D) To determine how well the project is progressing

E) All of the above are valid reasons

12. The bottom-up approach for estimating times and costs that uses costs from past projects that were similar to the current project is known as:

A) Detailed WBS work package estimates

B) Template method

C) Function point method

D) Time-phased cost estimates

E) Phase estimating

13.Which of the following top-down methods is used when projects closely follow past projects in features and costs and result in costs being assigned by percentages to major segments of the project?

A) Apportion

B) Function point

C) Phase estimating

D) Learning curve

E) Consensus

14.People working on prototype development needing time to interact with the design engineers after the design is completed is an example of:

A) Hidden interaction costs

B) Things going wrong on a project

C) Normal conditions not applying

D) Changes in project scope

E) None of these are correct

15.Design flaws being revealed after the fact, extreme weather conditions, and accidents occurring are examples of:

A) Hidden interaction costs

B) Things going wrong on a project

C) Normal conditions not applying

D) Changes in project scope

E) None of these are correct

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M92195555
  • Price:- $20

Priced at Now at $20, Verified Solution

Have any Question?


Related Questions in Operation Management

Corporate social responsibility impacts a number of a

Corporate social responsibility impacts a number of a company's stakeholders including: a) Communities, b) Consumers, c) Shareholders, and d) Employees. For this exercise: A. Please provide a specific example of a compan ...

Ventacare nursing homes provides private care for over 500

VentaCare Nursing Homes provides private care for over 500 residents in three different locations. The company employs 250 staff members with a variety of responsibilities including RN’s, nursing assistants, kitchen staf ...

Assignmentwhen forecasting the weather meteorologists rely

Assignment When forecasting the weather, meteorologists rely on a number of concrete predictive methods. They can collate quantitative data about the weather's current state, for example, or they can analyze how the weat ...

1 how many observations should a time study analyst plan

1. How many observations should a time study analyst plan for in an operation that has a standard deviation of 1.7 minutes per piece if the goal is to estimate the mean time per piece to within .4 minute with a confidenc ...

Compare the key components inherent in the national health

Compare the key components inherent in the national health insurance financing systems of two (2) different countries. Determine the impact that financing health insurance has on the economy of each country that you sele ...

1 what are the factors for determining whether to purchase

1. What are the factors for determining whether to purchase or strategically source an item? 2. From your personal and professional experiences, identify the traits that signify an organization is a “good corporate citiz ...

1 how does conflict arise in organizational negotiations2

1. How does conflict arise in organizational negotiations? 2. Choose one of the recent teacher strikes and write a one paragraph summary of the situation. Next write one or two paragraphs on how effective the strike was ...

1 the primary goal of operations is toprovide greater value

1. The primary goal of operations is to: Provide greater value to the customers and ultimately to the firm Make as much money for the company as possible Improve the quality of the product or service Reduce the cost of t ...

Root cause analysis is an effective approach to finding

Root Cause Analysis is an effective approach to finding systematic causes of problems. What are your thoughts about using the process to avoid the blame game that can occur in some health systems? Often there are systema ...

1 discuss investigate and research the following with your

1. Discuss, investigate, and research the following with your teammates: Often, community events are sponsored by corporations who claim that the reason they are involved is "to give back" to the community. However, on p ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As