1. General Foundry, Inc., a metal works plant in Milwaukee, has long been trying to avoid the expense of installing air pollution control equipment. The local environment protection group has recently given the foundry 16 weeks to install a complex air filter system on its main smokestack. General Foundry has been warned that it may be forced to close unless the device installed in the allotted period. Lester Harky, the managing partner, wants to make sure that installation of the filtering system progressed smoothly and on time.

General Foundry has identified the following eight activities that need to be performed and their sequential relationship.

Activity

Description

Time

(weeks)

Immediate

Predecessors

A

Build internal components

2

--

B

Modify roof and floor

4

--

C

Construct collection stack

2

A

D

Pour concrete and install frame

4

A, B

E

Build high-temperature burner

4

C

F

Install pollution control system

3

C

G

Install air pollution device

5

D, E

H

Inspect and test

2

F, G

a. Construct the appropriate network diagram.

b. Which jobs can be delayed without delaying the project completion time?

c. Can General Foundry complete the project on time? Why or why not?

d. Suppose Lester wants to shorten the completion time and his options are:
(1) Reduce activity D by one week, which costs $700/week;
(2) Reduce activity E by one week, which costs $800/week;
(3) Reduce activity G by one week, which costs $1000/week;

If General Foundry will save $2000 for each week that the earliest completion time is reduced, which single option, if any, should Lester choose?

2. The following table represents a plan for a project:

 

Time Estimates (days)

Job No.

Predecessor Job(s)

Optimistic

Most likely

Pessimistic

A

-

1

2

3

B

-

2

3

4

C

A

4

5

6

D

B

8

9

10

E

C, D

2

5

8

F

D

4

5

6

G

E

1

2

3

a. Construct the appropriate network diagram.

b. What is the critical path?

c. What is the expected completion time for the project and what is the variance of project completion time?

e. Is the probability that the project will take less than 18 days to complete larger than 50% or smaller than 50%?

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M91971618

Have any Question?


Related Questions in Operation Management

What would you do if your supervisor directed you to bribe

What would you do if your supervisor directed you to bribe other businesses to obtain contacts? is there legal protection for employees who report employer illegal behavior research the travel act and the fcpa. explain h ...

Assignmentdefine critical thinking what are the criteria in

Assignment: Define critical thinking. What are the criteria in which it might be evaluated? What are the biases involved in critical thinking? Explain a recent high-profile court case that has had to overcome such biases ...

1 centralized planning by a small group of corporate

1. Centralized planning by a small group of corporate executives; A. Can suffer the “ivory tower syndrome” that distorts top down view of the industry, ignoring key markets nuances B. Should never involve mid and lower l ...

There are what are called second generation rights which

There are what are called Second Generation rights, which include the rights of the poor and quality of life issues and these connect to the announcements about the future of the global economy, Third World poverty and s ...

Assignment questiondo you think that human reproductive

Assignment question: Do you think that human reproductive cloning is morally permissible? Do you think that it should be permitted by law? It is imperative that you justify and defend your position based on cogent argume ...

The life of a phone battery is normally distributed with a

The life of a phone battery is normally distributed with a mean of 1,100 days and a standard deviation of 60 days. Determine the following a. What fraction of batteries is expected to survive beyond 1,200 days b. what fr ...

Describe small business marketingidentify the components of

Describe small business marketing. Identify the components of a formal marketing plan. Describe the characteristics and value of a strong management team. Identify and explain the six forms of legal organization discusse ...

Many companies use their brand as a competitive advantage

Many companies use their brand as a competitive advantage. Given your knowledge about the global economy, identify three brands you believe have the strongest likelihood of remaining a source of advantage in the 21st cen ...

Securing digital informationscenario your company has

Securing Digital Information Scenario: Your company has experienced a major breach in Internet security. Your CSO has contacted the IAS department to develop a series of IAS security communications that acknowledges the ...

1 true or false- unlike some social ventures b corps are

1. True or False - Unlike some social ventures, B corps are concrete and measurable. 2. What is described as the most fulfilling aspect of B Corp certification? A. Quality products/services B. Community C. Public approva ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As