Find a news item within the past 6 months about a company that has benefitted from enterprise resource planning.

(i) Describe the company briefly - product/services, locations, customers

(ii) Describe the company's operations briefly - type of process

(iii) Describe how ERP has benefitted the company

2. MRP

Specialty Bikes Inc (SBI) assembles road bikes for recreational use. There has been a surge in road cycling with the baby boom generation. The assembly of the bike has the following BOM:

789_img.png

A = Finished assembled bike
HB = Handle bars
W = Wheels
C = Chain set with pedals
G = Gear set

The assembly department already has the frame which includes the seat. Orders for bikes and parts schedules to be received are as follows:

Orders for Bikes

Week

Bikes Ordered

5

300

6

200

7

400

Current on Order

HB

300 in week 3

W

200 in week 4

The inventory status is as follows:

Inventory Status






Part

A

HB

W

C

G

On Hand

100

50

150

200

300

Lead Time (Weeks)

2

2

2

0

0

Lot Size

LFL

300

LFL

250

LFL

Safety Stock

0

0

0

100

0

Requirement: Complete the MRP Records

Part

Lot

Lead 

On

Safety

 

 

 

 

 

 

 

 

No.

Size

Time

Hand

Stock

Weeks

1

2

3

4

5

6

7






Gross Requirements

 

 

 

 

 

 

 

 

 

 

 

 

Scheduled Receipts

 

 

 

 

 

 

 

 

 

 

 

 

Projected on Hand     

 







 

 

 

 

 

Net Requirements

 

 

 

 

 

 

 

 

 

 

 

 

Planned Order Receipts

 

 

 

 

 

 

 

 

 

 

 

 

Planned Order Releases

 

 

 

 

 

 

 

Part

Lot

Lead 

On

Safety

 

 

 

 

 

 

 

 

No.

Size

Time

Hand

Stock

Weeks

1

2

3

4

5

6

7






Gross Requirements

 

 

 

 

 

 

 

 

 

 

 

 

Scheduled Receipts

 

 

 

 

 

 

 

 

 

 

 

 

Projected on Hand     








 

 

 

 

 

Net Requirements

 

 

 

 

 

 

 

 

 

 

 

 

Planned Order Receipts

 

 

 

 

 

 

 

 

 

 

 

 

Planned Order Releases

 

 

 

 

 

 

 

Part

Lot

Lead 

On

Safety

 

 

 

 

 

 

 

 

No.

Size

Time

Hand

Stock

Weeks

1

2

3

4

5

6

7






Gross Requirements

 

 

 

 

 

 

 

 

 

 

 

 

Scheduled Receipts

 

 

 

 

 

 

 

 

 

 

 

 

Projected on Hand   








 

 

 

 

 

Net Requirements

 

 

 

 

 

 

 

 

 

 

 

 

Planned Order Receipts

 

 

 

 

 

 

 

 

 

 

 

 

Planned Order Releases

 

 

 

 

 

 

 

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M91705235
  • Price:- $40

Guranteed 36 Hours Delivery, In Price:- $40

Have any Question?


Related Questions in Operation Management

1 as discussed in the case amazon prime has been a

1. As discussed in the case, Amazon Prime has been a successful service for Amazon. Thoroughly discuss all aspects of the marketing mix as it relates to this service. 2. How do politics play a role in global procurement? ...

1 burger kings plan states that the company intends to

1. Burger King's plan states that the company intends to improve profitability by 7 percent, reduce customer complaints, maintain the company's market share, and develop a new breakfast food. Which part of the plan is re ...

1 describe various high-tech techniques that can be used to

1. Describe various high-tech techniques that can be used to enhance the quality of individual decisions and group decisions. ( please write long essay) 2. What is strategy implementation? What questions must strategy ma ...

Turnaround at nissanin 1999 nissan was in a state of

Turnaround at Nissan In 1999, Nissan was in a state of serious decline and had lost money in all but one of the previous eight years. Only Renault’s willingness to assume part of Nissan’s debt saved the Japanese company ...

1 compute the takt time minutes per unit for a system given

1. Compute the takt time (minutes per unit) for a system given the following data: There is a single worker per shift with a total time per shift of 460 minutes. There is/are 1 shift(s), and workers are given two 5 minut ...

Mozillarsquos crowdsourcing mystiquecase abstractcase

Mozilla’s Crowdsourcing Mystique case abstract: CASE ABSTRACT Mozilla, the California-based developer of the popular Firefox web browser, is a not-for-profit organization. More importantly, while it employs 250 people, a ...

1 what is the strengths and weaknesses of bugeting

1. What is the strengths and weaknesses of bugeting forecasting system? Do you believe the weaknesses can ever be overcome? If so how? If not, why not. 2. Assume you are opening a new recreational facilities business cal ...

Please consider the h1b visa question impliedly posed in

Please consider the H1B visa question impliedly posed in this article. Recognizing that the human capital or resource pillar of your supply chain/cycle will impact all other pillars, please address one of the following q ...

Instead of an 80 learning curve the supplier believes that

Instead of an 80% learning curve, the supplier believes that a 90% learning curve will be more indicative of what will occur in the future (starting at unit 51). What would be the unit cost of labor for the next 350 unit ...

1 the current equipment allows your production line to

1. The current equipment allows your production line to assemble 1760 widgets per day with a takt time of 4.00 minutes. A vendor is proposing their new equipment which would allow you to assemble 2120 widgets per day. Wh ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As