Ask Operation Management Expert

1. Which of the following represents an activity on an AON project network?

A) An arrow

B) A line

C) A node

D) Both A and B are correct

E) A, B, and C are all correct

2.Arrows on an AON project network represent:

A) An activity

B) Project flow

C) Dependency

D) Both B and C are correct

E) Both A and B are correct

3.Which of the following is provided by a project network but not by the work breakdown structure?

A) Dependencies

B) Sequencing

C) Interrelationships

D) Both A and B are correct

E) A, B, and C are all correct

4.Part of a project is to Develop Product Specifications. This is best classified as a(n)

A) Event

B) Path

C) Activity

D) Node

E) Milestone

5.The critical path in a project network is the

A) Shortest path through the network

B) Longest path through the network

C) Network path with the most difficult activities

D) Network path using the most resources

E) Network path with the most merge activities

6.An item on a project network is Design Software Completed. This is best described as a(n)

A) Event

B) Path

C) Activity

D) Node

E) Milestone

7.A sequence of connected, dependent activities is termed a(n)

A) Critical path

B) Parallel path

C) Activity chain

D) Path

E) Dependent chain

8.Which of the following is not one of the basic rules to follow when developing project networks?

A) An activity cannot begin until all preceding activities have been completed

B) Each activity must have a unique identification number

C) Conditional statements are allowed but looping statements are not allowed

D) An activity identification number must be larger that that of any preceding activities

E) Networks flow from left to right

9.________ activities must be completed immediately before a particular activity.

A) Merge

B) Burst

C) Predecessor

D) Successor

E) Critical

10.The forward pass in project network calculations determines the

A) Earliest time's activities can begin

B) Earliest time's activities can be finished

C) Duration of the project

D) Both A and B are correct

E) A, B, and C are all correct

11.The backward pass in project network calculations determines the

A) Latest time's activities can begin

B) Earliest time's activities can be finished

C) Critical path

D) Both A and C are correct

E) A, B, and C are all correct

12.The amount of time an activity can be delayed and yet not delay the project is termed

A) Total slack

B) Free slack

C) Critical float

D) Float pad

E) Slip pad

13.The laying pipe example in the text illustrates the concept of

A) Laddering

B) Hammock activities

C) Critical path

D) Concurrent engineering

E) Forward pass

14.Typically an activity on a project network represents

A) A single work package

B) One or more tasks from a work package

C) Several work packages

D) A sub-deliverable

E) A cost account

15.Concurrent engineering is a good example of good use of

A) Start to Start lags

B) Start to Finish lags

C) Finish to Finish lags

D) Finish to Start lags

E) Any of these could be correct

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M92195548
  • Price:- $20

Priced at Now at $20, Verified Solution

Have any Question?


Related Questions in Operation Management

Conflictdefine functional versus dysfunctional conflict in

Conflict Define functional versus dysfunctional conflict in a work group and explain how you can increase functional conflict and decrease dysfunctional conflict. Develop a response that includes examples and evidence to ...

For this assignment you will need to find 2 articles in

For this assignment, you will need to find 2 articles in business that can help describe what are IT strategic initiative being undertaken by an organization are like. Choose a different organization for each of the arti ...

Coping with problems joe is a little nervous he has just

Coping With Problems Joe is a little nervous. He has just been transferred from another plant to take over a production line. Production is down and there is a serious problem with absenteeism. To make matters worse, the ...

Over 30 years ago michael porter identified a holistic

Over 30 years ago Michael Porter identified a holistic approach to understanding how competitive forces shape strategy. He posited that the only way to truly insulate an organization from underlying economic volatility i ...

You are the contracting officer for an air-to-ground

You are the contracting officer for an air-to-ground missile development program. A contract for pre-production models of the missile was awarded by your predecessor and the contractor is behind schedule. In a program me ...

The ikea case provides an excellent opportunity to apply

The IKEA case provides an excellent opportunity to apply strategic management concepts to a large privately-held company that is expanding into India. IKEA is a Netherlands-based Swedish company with a presence in 44 cou ...

Can you answer for me the following questions about social

Can you answer for me the following questions about social loafing and the three main causes of free-riding. 1. Give a description of the phenomenon of social loafing. 2. Give a description of the phenomenon of free-ridi ...

1 analyzing the bridgestonefirestone and ford motor company

1. Analyzing the Bridgestone/Firestone and Ford motor company, is it sufficient to use the ISO/QS 9000 standards as the main basis of vendor/product selection? 2. What position to these cars company ( 1. Volkswagen, 2. F ...

Research the effect of primary and secondary seat belt laws

Research the effect of primary and secondary seat belt laws on the occurrence of motor-vehicle injuries and fatalities. Explain how epidemiologic studies influenced the development of current seat belt laws. Describe how ...

Please provide a brief paragrap of the key takaways from

Please provide a brief paragrap of the key takaways from each of the following topics: Designing Clear Visuals in business reports Designing Successful Documents and Websites Writing Winning Proposals

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As