1. Use the following information to construct a "Tracking Gantt" chart using MS Project.

Activities Duration Preceding
A 5 days none
B 4 days A
C 3 days A
D 6 days B, C
E 4 days
F 2 days D, E

Highlight project status on day 14 using the tracking option and assuming that all tasks to date have been completed on time. Print/capture the output file.

2. Using the information in Problem 1, highlight the project's status on day 14 but assume that activity D has not yet begun. What would the new tracking Gantt chart show? Print/capture the output file.

3. Use the following table to calculate project schedule variance based on the units listed. (Figures are in thousands.)

Schedule Variance Work Units

 

A

B

C

D

E

F

Total

Planned Value

20

15

10

25

20

20

110

Earned Value

10

10

10

20

25

25

 

Schedule variance

 

 

 

 

 

 

 

4. Using the data in the table below, complete the table by calculating the cumulative planned and cumulative actual monthly budgets through the end of June. Complete the earned value column on the right. Assume the project is planned for a 12-month duration and $250,000 budget.

Activity                        Jan     Feb               Mar Apr         May Jun      Plan % C Value

Staffing                        8        7                                              15      100_______

Blueprinting                              4        6                                    10      100_______

Prototype

Development                                     2        8                           10      70 _______

Full Design                                                   3        8        10     21      67________

Construction                                                          2        30     32      25________

Transfer                                                                           10     10      0

Monthly Plan ____________________________________________________

Cumulative _______________________________________________

Monthly Actual             10      15      6        14      9       40

Cumul. Actual____________________________________________________________

5. Using the data from Problem 4, calculate the following values:

Schedule Variances

Planned Value (PV)

Earned Value (EV)
Schedule Performance Index (SPI)
Estimated Time to Completion

Cost Variances
Actual Cost of Work Performed (AC)
Earned Value (EV)
Cost Performance Index (CPI)
Estimated Cost to Completion

Operation Research, Management Studies

  • Category:- Operation Research
  • Reference No.:- M91892336
  • Price:- $65

Priced at Now at $65, Verified Solution

Have any Question?


Related Questions in Operation Research

Explain the mathematical system of or and linear

Explain the Mathematical system of OR and linear programming

Your presentation should include the followingintroduction

Your presentation should include the following: Introduction (5-6 slides) Explain the importance of evidence-based decision making in health care. Discuss how this evidence applies to patient care outcomes, financial out ...

Assignment - country analysis this is a marketing and

Assignment - Country Analysis This is a marketing and analysis paper on two countries, South Korea and India. The objective is to determine if both countries are a great market for TESLA to expand their business in a glo ...

Real estate property analysisresearch the property you

Real Estate Property Analysis Research the property you selected in your Local Real Estate Opportunities activity. Using the newspaper listing from your exploration, either go online to the real estate agency that is lis ...

Assignment requirementassignment reflective writing aims to

Assignment Requirement Assignment Reflective writing aims to get you to think about your learning and understand your learning experiences. When students writing Assignment 3 need to follow steps: 1. Evaluate the effecti ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As