1. Determining Critical Path and Activity Slack

Assume we have a set of activities, their expected durations, and immediate predecessors. Enter this information using MS Project to produce a Gantt chart - enable project summary.

(a) Identify the critical path.

(b) Identify activity slack times that are non-zero and record in the table below.

Activity

Duration
(days)

Predecessors

Free Slack

Total Slack

A

6

....

 

 

B

7

 

 

 

C

5

A

 

 

D

3

A, B

 

 

E

4

C

 

 

F

5

D

 

 

G

8

E, F

 

 

H

3

F, G

 

 

Now, now assume that activity C has taken 8 days past its anticipated duration to complete.

(c) How does the project's schedule duration change?

(d) Why does the duration change?

(e) Is there a new critical path? If so, what is it?

2. Refer to the task/activity table shown here.Enter this information using MS Project to produce a Gantt chart - enable project summary. Assume that each resource has been assigned to the project activity on a full-time basis.

Construct System 20 days Design System Harry Smith, Biil Plant
Test System 10dyas Gather Requirements, Construct System (FS with minus 10 day lag/lead) Kate Stone, Bill Plant
Revise System from Test 5days Test system Harry Smith, Biil Plant
Deploy System s days Revise system from test Ryan Burns

(a) Using the above information, produce a resource usage sheet identifying the total number of hours and daily commitments of each project team member. Record the total hours for each resource.

Resource

Hours

Bill Plant

 

Harry Smith

 

Kate Stone

 

Ryan Burns

 

Sue Peterson

 

(b) Identify any members of the project team who have been overassigned.

(c) Determine and record the specific dates when there is a conflict in the resource assignment schedule.

(d) Using the information above, describe how you could level the resource load to remove conflicts? What is affected by the change? What assumptions are made?

3. Use the following information to construct a tracking Gantt chart using MS Project - enable project summary.

Activities Duration Preceding Activites  Percent Complete
A 2 days None 100%
B 4 days A 100%
C 6days B 35%
D 3days B,C 0%
E 4 days B 0%
F 5 days C,E 0%

(a) What is the total % complete for the project overall?

(b) What is the Actual Duration for the project overall?

(c) What is the Remaining Duration for the project overall?

4. Assume you have collected the following data for your project. The roject budget is $90,000 and it is planned to last a total of 120 workdays. After collecting status partway through the project., you have collected the following status information,

PV = $100,000

EV = $80,000

AC = $65,500

Schedule Performance Index(SPI)
Estimated Time to Completion

Cost Performance Index(CPI)
Estimated Cost to Completion

Based on these values, estimate the time and budget necessary to complete the project.

(a) Describe how would you evaluate these findings? Are they good news or bad news?

(b) What could possibly cause this situation to occur? Be specific with examples.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M91761415

Have any Question?


Related Questions in Operation Management

Conflictdefine functional versus dysfunctional conflict in

Conflict Define functional versus dysfunctional conflict in a work group and explain how you can increase functional conflict and decrease dysfunctional conflict. Develop a response that includes examples and evidence to ...

For this assignment you will need to find 2 articles in

For this assignment, you will need to find 2 articles in business that can help describe what are IT strategic initiative being undertaken by an organization are like. Choose a different organization for each of the arti ...

Coping with problems joe is a little nervous he has just

Coping With Problems Joe is a little nervous. He has just been transferred from another plant to take over a production line. Production is down and there is a serious problem with absenteeism. To make matters worse, the ...

Over 30 years ago michael porter identified a holistic

Over 30 years ago Michael Porter identified a holistic approach to understanding how competitive forces shape strategy. He posited that the only way to truly insulate an organization from underlying economic volatility i ...

You are the contracting officer for an air-to-ground

You are the contracting officer for an air-to-ground missile development program. A contract for pre-production models of the missile was awarded by your predecessor and the contractor is behind schedule. In a program me ...

The ikea case provides an excellent opportunity to apply

The IKEA case provides an excellent opportunity to apply strategic management concepts to a large privately-held company that is expanding into India. IKEA is a Netherlands-based Swedish company with a presence in 44 cou ...

Can you answer for me the following questions about social

Can you answer for me the following questions about social loafing and the three main causes of free-riding. 1. Give a description of the phenomenon of social loafing. 2. Give a description of the phenomenon of free-ridi ...

1 analyzing the bridgestonefirestone and ford motor company

1. Analyzing the Bridgestone/Firestone and Ford motor company, is it sufficient to use the ISO/QS 9000 standards as the main basis of vendor/product selection? 2. What position to these cars company ( 1. Volkswagen, 2. F ...

Research the effect of primary and secondary seat belt laws

Research the effect of primary and secondary seat belt laws on the occurrence of motor-vehicle injuries and fatalities. Explain how epidemiologic studies influenced the development of current seat belt laws. Describe how ...

Please provide a brief paragrap of the key takaways from

Please provide a brief paragrap of the key takaways from each of the following topics: Designing Clear Visuals in business reports Designing Successful Documents and Websites Writing Winning Proposals

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As