Ask Operation Management Expert

1 Activities which can take place at the same time are termed

Parallel activity.

Merge activity.

Burst activity.

Critical path.

Independent activity.

2 An uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives is termed a

Random chance.

Bad luck.

Risk.

Hazard.

Disaster.

3 Based on the following, which event should you be most concerned about?

Risk Event

Likelihood

Impact

Bad weather

2

3

Design flaw

3

5

Accident

1

5

Shipment delay

2

2

Power outage

1

5

Accident

Shipment delay

Bad weather

Power outage

Design flaw

4 If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?

Check to see which activities are on the critical path.

Check to see which activities cost the least.

Check to see which activities have the most slack.

Check to see which activities have the highest risk.

Check to see which activities have the longest duration.

5 Information to develop a project network is collected from the

Budget.

Organization breakdown structure.

Responsibility matrix.

Project proposal.

Work breakdown structure.

6 One common mistake made early in the risk identification process is to

Not consider all possibilities.

Encourage participants be over optimistic.

Give too much attention to past events.

Support participants being over pessimistic.

Focus on consequences and not on the events that could produce consequences.

7 Risks are evaluated in terms of

Impact and cost.

Likelihood and cost.

Time and impact.

Cost and schedule.

Likelihood and impact.

8 The amount of time an activity can be delayed and yet not delay the project is termed

Total slack.

Free slack.

Critical float.

Slip pad.

Float pad.

9 The attempt to recognize and manage potential and unforeseen trouble spots that may occur when a project is implemented is known as

Risk management.

Contingency planning.

Risk forecasting.

Scenario analysis.

Disaster protection.

10 The backward pass in project network calculations determines all of the following EXCEPT

Earliest time an activity can finish.

How long an activity can be delayed.

Latest time an activity can begin.

The critical path.

Latest time an activity can finish.

11 The cost impact of a risk event occurring as a project proceeds through its life cycle tends to

Remain about the same.

Drop sharply and then level out.

Rise sharply and then level out.

Slowly rise.

Slowly drop.

12 The critical path in a project network is the

Longest path through the network.

Shortest path through the network.

Network path with the most difficult activities.

Network path with the most merge activities.

Network path using the most resources.

13 The forward pass in project network calculations determines all of the following EXCEPT

Duration of the project.

Earliest time an activity can finish.

How soon the project can finish.

The critical path.

Earliest time an activity can begin.

14 The initial step in the risk management process is to

Set aside budget funds for managing the risks.

Assess the risk potential.

Appoint a risk manager.

Identify the risks.

Determine the level of acceptable risk.

15 The likelihood the original critical path(s) will change once the project is initiated is referred to as

Rigidity.

Concurrent engineering.

Sensitivity.

Flexibility.

Resilience.

16 When translated into a project network, a work package will become

An arrow.

A milestone.

One or more activities.

A single activity.

A critical path.

17 Which of the following correctly calculates the early finish for an activity?

LF + SL

LF + DUR

ES + SL

LS + DUR

ES + DUR

18 Which of the following correctly calculates the late start for an activity?

EF - DUR

LF - DUR

ES - DUR

LF - SL

ES - SL

19 Which of the following will correctly calculate the total slack in an activity?

LS - ES

LF - ES

LF - EF

LS - LF

Either LS - ES or LF - EF

20 ________ activities must be completed immediately before a particular activity.

Merge

Burst

Successor

Predecessor

Parallel

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M92872266
  • Price:- $20

Priced at Now at $20, Verified Solution

Have any Question?


Related Questions in Operation Management

Conflictdefine functional versus dysfunctional conflict in

Conflict Define functional versus dysfunctional conflict in a work group and explain how you can increase functional conflict and decrease dysfunctional conflict. Develop a response that includes examples and evidence to ...

For this assignment you will need to find 2 articles in

For this assignment, you will need to find 2 articles in business that can help describe what are IT strategic initiative being undertaken by an organization are like. Choose a different organization for each of the arti ...

Coping with problems joe is a little nervous he has just

Coping With Problems Joe is a little nervous. He has just been transferred from another plant to take over a production line. Production is down and there is a serious problem with absenteeism. To make matters worse, the ...

Over 30 years ago michael porter identified a holistic

Over 30 years ago Michael Porter identified a holistic approach to understanding how competitive forces shape strategy. He posited that the only way to truly insulate an organization from underlying economic volatility i ...

You are the contracting officer for an air-to-ground

You are the contracting officer for an air-to-ground missile development program. A contract for pre-production models of the missile was awarded by your predecessor and the contractor is behind schedule. In a program me ...

The ikea case provides an excellent opportunity to apply

The IKEA case provides an excellent opportunity to apply strategic management concepts to a large privately-held company that is expanding into India. IKEA is a Netherlands-based Swedish company with a presence in 44 cou ...

Can you answer for me the following questions about social

Can you answer for me the following questions about social loafing and the three main causes of free-riding. 1. Give a description of the phenomenon of social loafing. 2. Give a description of the phenomenon of free-ridi ...

1 analyzing the bridgestonefirestone and ford motor company

1. Analyzing the Bridgestone/Firestone and Ford motor company, is it sufficient to use the ISO/QS 9000 standards as the main basis of vendor/product selection? 2. What position to these cars company ( 1. Volkswagen, 2. F ...

Research the effect of primary and secondary seat belt laws

Research the effect of primary and secondary seat belt laws on the occurrence of motor-vehicle injuries and fatalities. Explain how epidemiologic studies influenced the development of current seat belt laws. Describe how ...

Please provide a brief paragrap of the key takaways from

Please provide a brief paragrap of the key takaways from each of the following topics: Designing Clear Visuals in business reports Designing Successful Documents and Websites Writing Winning Proposals

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As