1. A contractor's quotation for $1,500,000 includes $ 250,000 as prelims. This project is to be completed within 5 months. Having worked for 2 months, the contractor submits the first bill for $175,000.00. Using this scenario as an example,

(a) reason out which method should be used for valuing prelims (i.e. time related or value related);

(b) compute the amount you would certify;

(c) explain how such ambiguities be avoided; and

(d) note a strategy that can be brought to bear to incentivize/penalize slow financial progress other than liquidated damages

2. Prepare a detailed procurement plan for the following situation. Make reasonable assumptions clearly stating what these assumptions are:

A client wishes to refurbish a large hotel during the off-season (June to October). A decision has been made to manage this project using in-house staff. One of the main jobs involves re-tiling 60 toilets. The client has decided to use a number ofsmall contractors on a labour only basis. Prepare a procurement program for this project. Assume that the Project Manager has to submit all quotations to the Managing Director for approval.

3. A government department has a practice of specifying the monetary value of the tender bond by basing it on a certain percentage of the estimated cost. For example, if the estimated price is 100,000, the tender bond isset at 3,000. Likewise, if the estimated price is 1,000,000, the bid bond is set at 30,000. During an informal social chat at a pub, the procurement office who works at the said government department discusses the percentage they hold on tender bonds in response to a question raised by one of his friends. You are not a friend of the procurement officer. What problems can arise in relation to Tender Conditions? Base your judgment on focusing on a known set of tender conditions.

4. A client is interested in constructing a five storey office building (ground and five upper floors). He has requested you to provide a P90 estimate. Designs are at the preliminary stage. The internal floor areas for each floor (from ground to top floor) is approximately 1500, 1500, 1250, 1000, 1000, and 750 sq.m. respectively. The ground floor is to be laid with expensive granite slabs.

Ground conditions are poor requiring piling. A similar building close to the proposed site was constructed in 2010 for $ 20M with a total floor area of 10,000 sq.m. but ground conditions were good. Prepare an estimate to completion taking into account of all costs assuming that the building would take 3 years to complete from now. Assume any information not given. Use format given in course book.

5. Evaluate the decision to tender given the following information: Line of credit from bank $2M (total)

Budgeted turnover (first six months): $75M (as per business plan)

Month 1 Month 2 Month 3 Month 4 Month 5 Month 6

Forecast monthly TO of current projects - Workload($) 5M 15M 20M 20M 10M 5M

Cumulative cash flow forecast ($) +1M -0.5M -1M -1M -1.2M -0.9M

Forecast monthly TO of project to be tendered approx. value $21M 2M 3M 5M 5M 4M 2M

Bid project cumulative cash flow ($) - 0.5M -0.75M -1M X + 0.5M +0.5M

Bond balance sheet ($) 0.5M 0.75M 0.5M 1.5M 0.25M 0.25M

TO - Turnover

Note: Take the value of 'X' (month 4 for bid project) as follows:

If your surname starts with:

A to E, take as 0

F to J, take as -0.5

K to O, take as +0.5

P to T, take as -1.0

U to Z, take as +1.0

6. A value espoused by a contracting organization is 'ethical construction'. In response to a tender submission, you have been asked by your manager to provide a paragraph on this issue. List five practices that may impress a prospective client demonstrating similar values. Page 3 of 4

7. Prepare a payment claim given the following information: The payment claim is made under theBCIPA 2004. The contract does not provide for payment of materials on site. Landscape work hasn't started. Take retentions at 10% with a ceiling of 5% of Base Contract Sum. Take value of variations completed are as follows:

If your surname starts with:

A to E, take as 10,000

F to J, take as 12,000

K to O, take as 15,000

P to T, take as 17,000

U to Z, take as 20,000

Payments received to date 10,000 (excluding GST) Priced Quotation Payment Claim 2: Details

Price % complete Value of work done Excavations 10,000.00 Excavations 80

Concrete Work 35,000.00 Concrete Work 80

Metal Windows and Doors 15,000.00 Metal Windows and Doors 60

Electrical 10,000.00 Electrical 40 Painting 30,000.00 Painting 0 Base Contract 100,000.00 Base contract

Prime cost sum for electrical fittings 4000.00

As per receipts submitted but overheads and profits add 4,500.00

Provisional sum for landscape work 6,000.00

Contingency Sum 10,000.00

Materials at site 5,000.00

Contract Price 120,000.00

Add: GST 10% 12,000.00

Contract Price

including GST 132,000.00Page 4 of 4

8. Given the following, calculate the SQP for each of the tenders and the adjusted evaluation price:

a. Number of tenderers - 3 (X,Y, Z)

b. NPA grade range - 8

c. NPA for tenderers X, Y & Z are 8, 4, and 0

d. Base estimate is $ 100,000

e. Tender prices of X, Y, Z are $ 110,000, $120,000, $ 130,000

9. 'Most companies use cost-plus pricing - is this because it is better, or the most convenient? If most companies use cost-plus pricing, you'd think it must be the best method. After all, if a firm doesn't cover its costs with its price, it is out of business. So isn't cost-plus pricing the only method that will ensure long-term prosperity of the company?' Respond using not more than a page.

10. In what ways can a contractor demonstrate 'value for money'? List five ways

Homework Help/Study Tips, Others

  • Category:- Homework Help/Study Tips
  • Reference No.:- M91603921

Have any Question?


Related Questions in Homework Help/Study Tips

Review the website airmail service from the smithsonian

Review the website Airmail Service from the Smithsonian National Postal Museum that is dedicated to the history of the U.S. Air Mail Service. Go to the Airmail in America link and explore the additional tabs along the le ...

Read the article frank whittle and the race for the jet

Read the article Frank Whittle and the Race for the Jet from "Historynet" describing the historical influences of Sir Frank Whittle and his early work contributions to jet engine technologies. Prepare a presentation high ...

Overviewnow that we have had an introduction to the context

Overview Now that we have had an introduction to the context of Jesus' life and an overview of the Biblical gospels, we are now ready to take a look at the earliest gospel written about Jesus - the Gospel of Mark. In thi ...

Fitness projectstudents will design and implement a six

Fitness Project Students will design and implement a six week long fitness program for a family member, friend or co-worker. The fitness program will be based on concepts discussed in class. Students will provide justifi ...

Read grand canyon collision - the greatest commercial air

Read Grand Canyon Collision - The greatest commercial air tragedy of its day! from doney, which details the circumstances surrounding one of the most prolific aircraft accidents of all time-the June 1956 mid-air collisio ...

Qestion anti-trustprior to completing the assignment

Question: Anti-Trust Prior to completing the assignment, review Chapter 4 of your course text. You are a manager with 5 years of experience and need to write a report for senior management on how your firm can avoid the ...

Question how has the patient and affordable care act of

Question: How has the Patient and Affordable Care Act of 2010 (the "Health Care Reform Act") reshaped financial arrangements between hospitals, physicians, and other providers with Medicare making a single payment for al ...

Plate tectonicsthe learning objectives for chapter 2 and

Plate Tectonics The Learning Objectives for Chapter 2 and this web quest is to learn about and become familiar with: Plate Boundary Types Plate Boundary Interactions Plate Tectonic Map of the World Past Plate Movement an ...

Question critical case for billing amp codingcomplete the

Question: Critical Case for Billing & Coding Complete the Critical Case for Billing & Coding simulation within the LearnScape platform. You will need to create a single Microsoft Word file and save it to your computer. A ...

Review the cba provided in the resources section between

Review the CBA provided in the resources section between the Trustees of Columbia University and Local 2110 International Union of Technical, Office, and Professional Workers. Describe how this is similar to a "contract" ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As