1 A ________ Gantt chart is a simple and effective way to depict progress on a project.

Control

Tracking

Simple

Baseline

Variance

2 A project monitoring system involves all of the following EXCEPT

Determining what data to collect.

Adjusting the data.

Reporting current progress.

Analysis of the data.

Determining how, when, and who will collect the data.

3 An analysis carried out during and shortly after the project life cycle that attempts to capture positive and negative learning is represented in which of the following?

Performance evaluation

Lessons learned

Scenario analysis

Strategic objectives

Variance analyses

4 Jessica just received the following information on her project: PV = 200, EV = 300, AC = 250, BAC = 1500, EAC = 1208. In terms of cost at completion.

The project will currently finish under budget.

The project will currently finish on budget.

The project will currently finish over budget.

The project will currently finish behind schedule.

There is insufficient information to draw conclusions.

5 Jim receives the following information on his project: PV = 1000, EV = 1200, AC = 800, BAC = 2000, EAC = 1333. How is the project doing in terms of schedule?

The same amount of work has been done than planned

More work has been done than planned

The project has cost less than planned

Less work has been done than planned

There is not enough information to draw a conclusion

6 Nancy tells her supervisor that as of right now, $1.05 worth of work has been accomplished for each $1 worth of scheduled work. Nancy got this information from viewing the

TCPI.

CPI.

SPI.

SV.

PCIB.

7 The cost variance for a project is calculated by

EV - PV.

PV - EV.

AC - SV.

CV - EV.

EV - AC.

8 The earned value system starts with the time-phased costs that provide the project baseline, which is called the

Earned value of work scheduled.

Planned budgeted value of work scheduled.

Scheduled value of work completed.

Scheduled value of work scheduled.

Planned budgeted value of work completed.

9 The first step in the project control process for measuring and evaluating project performance is to

Review the project priority matrix.

Determine the project objectives.

Analyze the project budget.

Set a baseline plan.

Determine the project deliverables.

10 The following are general tips for conducting performance reviews EXCEPT

Be fair and consistent in your treatment of all team members.

Use other team members' performance as a method to compare and evaluate.

Begin the process by asking the individual to evaluate his or her own contributions to the project.

When you have to be critical, focus the criticism on specific examples of behavior and not on the individual personally.

Treat the review as only one point in an ongoing process.

11 The most common circumstance for project closure is simply a ________ project.

Successful

Completed

Over-budget

Underachieving

Overdue

12 The purpose of project evaluation is to assess how well

The project team and team members performed.

The project team, team members and project manager performed.

The project team performed.

The project manager performed.

The team members performed.

13 The schedule variance for a project is calculated by:

PV - EV

AC - SV

CV - EV

EV - PV

EV - AC

14 The third step in the project control process for measuring and evaluating project performance is to

Compare the plan against actual performance.

Analyze inputs to the control system.

Review spending with team members.

Review the baseline plan with top management.

Measure both progress and performance.

15 The typical mechanism for the evaluation of teams is normally

A survey completed by the team members.

A survey completed by the internal or external customers.

A survey completed by members of top management.

An analysis by an outside consultant.

A personal interview of each team member.

16 When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the

0/100 percent rule.

Work complete rule.

Task complete rule.

Degree complete rule.

Percent complete rule.

17 Which of the following methods will measure the cost efficiency of the work accomplished to date?

AC/CV

SV/CV

EV/PV

EV/AC

AC/SV

18 Which of the following would NOT be appropriate to assess when evaluating team performance?

Effectiveness of group decisions

How well the team performed in terms of time, cost, and specifications

Individual strengths and weaknesses

Customer satisfaction with project deliverables

Trust among group members

19 Which performance index is the most potentially misleading?

EV

CV

EAC

CPI

SV

20 ________ of lessons learned are designed to improve performance on current and future projects.

Culminations

Retrospectives

Evolutions

Corrective action plans

Introspectives

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M93049533
  • Price:- $20

Priced at Now at $20, Verified Solution

Have any Question?


Related Questions in Operation Management

Conflictdefine functional versus dysfunctional conflict in

Conflict Define functional versus dysfunctional conflict in a work group and explain how you can increase functional conflict and decrease dysfunctional conflict. Develop a response that includes examples and evidence to ...

For this assignment you will need to find 2 articles in

For this assignment, you will need to find 2 articles in business that can help describe what are IT strategic initiative being undertaken by an organization are like. Choose a different organization for each of the arti ...

Coping with problems joe is a little nervous he has just

Coping With Problems Joe is a little nervous. He has just been transferred from another plant to take over a production line. Production is down and there is a serious problem with absenteeism. To make matters worse, the ...

Over 30 years ago michael porter identified a holistic

Over 30 years ago Michael Porter identified a holistic approach to understanding how competitive forces shape strategy. He posited that the only way to truly insulate an organization from underlying economic volatility i ...

You are the contracting officer for an air-to-ground

You are the contracting officer for an air-to-ground missile development program. A contract for pre-production models of the missile was awarded by your predecessor and the contractor is behind schedule. In a program me ...

The ikea case provides an excellent opportunity to apply

The IKEA case provides an excellent opportunity to apply strategic management concepts to a large privately-held company that is expanding into India. IKEA is a Netherlands-based Swedish company with a presence in 44 cou ...

Can you answer for me the following questions about social

Can you answer for me the following questions about social loafing and the three main causes of free-riding. 1. Give a description of the phenomenon of social loafing. 2. Give a description of the phenomenon of free-ridi ...

1 analyzing the bridgestonefirestone and ford motor company

1. Analyzing the Bridgestone/Firestone and Ford motor company, is it sufficient to use the ISO/QS 9000 standards as the main basis of vendor/product selection? 2. What position to these cars company ( 1. Volkswagen, 2. F ...

Research the effect of primary and secondary seat belt laws

Research the effect of primary and secondary seat belt laws on the occurrence of motor-vehicle injuries and fatalities. Explain how epidemiologic studies influenced the development of current seat belt laws. Describe how ...

Please provide a brief paragrap of the key takaways from

Please provide a brief paragrap of the key takaways from each of the following topics: Designing Clear Visuals in business reports Designing Successful Documents and Websites Writing Winning Proposals

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As