ZXC Firm has the following information to determine Predetermine overhead rate for Standard Costing:
Estimated total manufacturing overhead costs $1,000,000
Estimated total amount of the allocation base at the level of projected activity 10,000 direct hours labor
What is the Predetermined overhead rate?