Q1) Let the following table:
|
PRET. ACT
|
TIME ESTIMATES (days)
|
Activity
|
|
to
|
tml
|
tp
|
te
|
A
|
-
|
6
|
6
|
6
|
|
B
|
A
|
4
|
5
|
6
|
|
C
|
A
|
2
|
4
|
6
|
|
D
|
B
|
4
|
6
|
8
|
|
E
|
C
|
1
|
3
|
5
|
|
F
|
D
|
1
|
5
|
3
|
|
i) What is the probability of this project being completed earlier than 19 days?
Between 13 and 15 days?
Determine the completion time and the standard deviation (σ) for project round off standard deviation to the nearest hundredth: two decimal places.
ii) What is the completion time at 95% confidence level?