Question 1

A GANTT chart represents mainly

Answer

an immediate identification of predecessor task.

a record-keeping device used in scheduling activities.

a general identifier.

the number of workers directly involved in the project.

Question 2

A PERT/CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 8 days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is:
Answer

7.0

7.5

8.0

8.5

Question 3

A PERT/CPM activity has an optimistic time estimate of 4 days, a most likely time estimate of 6 days, and a pessimistic time estimate of 10 days. The standard deviation of this activity is:
Answer

7/6

1/3

2/3

1.0

Question 4

A list of the tasks, broken down into modules, components, and individual tasks, is called a
Answer

work breakdown structure (WBS).

PERT.

planning matrix.

critical path.

Question 5

A work breakdown structure breaks down a project into
Answer

weeks.

areas.

arcs.

modules.

Question 6

Consider the following project.

 

What is the critical path?
Answer

ACFG

ADFG

BEG

ACDFG

Question 7

Consider the following project.

 

What is the minimum possible time for completing this project?
Answer

15 days

16 days

18 days

20 days

Question 8

Consider the following project.

Compute the slack time for activity C.
Answer

0

4

2

3

Question 9

Consider the following project.

What is the latest possible time that Activity E can be started without delaying the completion of the project?
Answer

8

3

7

9

Question 10

Consider the following project.

What is the latest time that activity B can start without delaying the project?
Answer

0

8

4

7

Question 11

Consider the following project.

What is the latest time that activity B can finish without delaying any other activities?
Answer

0

8

9

4

Question 12

Consider the following project.

Determine the critical path.
Answer

ACEH

BCEH

BDFH

BDGH

Question 13

Consider the following project.

Determine the estimated completion time of the project.
Answer

23 days

22 days

25 days

20 days

Question 14

Consider the following project.

 

Determine the slack for activity D.
Answer

2 days

4 days

6 days

5 days

Question 15

Consider the following project.

Determine the slack for activity F.
Answer

2 days

3 days

4 days

5 days

Question 16

Consider the following project.

How much can activity F be delayed without delaying the project completion?
Answer

1 day

2 days

3 days

4 days

Question 17

Elements of project planning include
Answer

defining project objectives.

identifying activities to crash.

calculating expected times and standard deviations.

conducting a "lessons learned" session.

Question 18

If an activity cannot be delayed without affecting the entire project, then it is a ________ activity.
Answer

completed

critical

crashed

normal

Question 19

If t is the expected completion time for a given activity, then:
Answer

LF = LS - t

EF = ES - t

EF = ES + t

EF = LS - t

Question 20

In a CPM/PERT network the critical path is the
Answer

lowest path through the network.

highest path through the network.

shortest path through the network.

longest path through the network.

Question 21

Joe used a project management software package and has determined the following results for a given project:

What is the probability of completing the project within 20 days?
Answer

0.3849

0.8849

0.1151

0.7642

Question 22

Joe used a project management software package and has determined the following results for a given project.:

What is the probability of completing the project over 20 days?
Answer

0.3849

0.8849

0.1151

0.7642

Question 23


Once a project is underway, the project manager is responsible for the
Answer

people.

cost.

time.

All of these

Question 24


Project control involves
Answer

crashing.

three time estimates.

a backward or forward pass.

earned value analysis.

Question 25

Project management differs from management of more traditional day-to-day activities because
Answer

it has limited time frame.

it has an unlimited budget.

it is more expensive.

it involves more of the workforce.

Question 26

The LS and LF are calculated using the
Answer

backward pass through the network.

forward pass through the network.

values for ES and EF.

backward and forward pass through the network.

Question 27


The activities that must be completed prior to the start of an activity in question are called the immediate ________ of the activity in question.
Answer

successors

predecessors

successors and predecessors

followers

Question 28

The critical path is the ________ path through the network.
Answer

longest

shortest

straightest

most expensive

Question 29


The normal cost for an activity is $7,000 and the crash cost is $12,000. The normal time to complete this activity is 8 days and crash time is 4 days. If this activity is crashed by 2 days it will cost an additional:
Answer

$1000

$1250

$2000

$2500

Question 30


Which of these statements regarding project crashing is true?
Answer

Crashing is not possible unless there are multiple critical paths.

Activities not on the critical path cannot become critical after crashing.

Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.

Crashing a project often reduces the time it takes for lengthy or complex, but noncritical activities.

Save and Submit

Click Save and Submit to save and submit. Click Save All Answers to save all answers. Click Close Window to close window.

Applied Statistics, Statistics

  • Category:- Applied Statistics
  • Reference No.:- M9434951
  • Price:- $60

Priced at Now at $60, Verified Solution

Have any Question?


Related Questions in Applied Statistics

Question onea a factory manager claims that workers at

QUESTION ONE (a) A factory manager claims that workers at plant A are faster than those at plant B. To test the claim, a random sample of times (in minutes) taken to complete a given task was taken from each of the plant ...

You are expected to work in groups and write a research

You are expected to work in groups and write a research report. When you work on your report, you need to use the dataset, and other sources such as journal articles. If you use website material, please pay attention to ...

Assignment -for each of the prompts below report the

Assignment - For each of the prompts below, report the appropriate degrees of freedom, t statistic, p-value and plot using the statistical software platform of your choice (R/STATA) 1) A sample of 12 men and 14 women hav ...

Assignment - research topicpurpose the purpose of this task

Assignment - Research topic Purpose: The purpose of this task is to ensure you are progressing satisfactorily with your research project, and that you have clean, useable data to analyse for your final project report. Ta ...

Assessment task -you become interested in the non-skeletal

Assessment Task - You become interested in the non-skeletal effects of vitamin D and review the literature. On the basis of your reading you find that there is some evidence to suggest that vitamin D deficiency is linked ...

Part a -question 1 - an analyst considers to test the order

PART A - Question 1 - An analyst considers to test the order of integration of some time series data. She decides to use the DF test. She estimates a regression of the form Δy t = μ + ψy t-1 + u t and obtains the estimat ...

Medical and applied physiology experimental report

Medical and Applied Physiology Experimental Report Assignment - Title - Compare the working and spatial memory by EEG. 30 students were tested (2 memory games were played to test their memory - a card game and a number g ...

Business data analysis computer assignment -part 1

Business Data Analysis Computer Assignment - PART 1 - Economists believe that high rates of unemployment are linked to decreased life satisfaction ratings. To investigate this relationship, a researcher plans to survey a ...

Question - go to the website national quality forum nqf

Question - Go to the website, National Quality Forum (NQF), located in the Webliography, and download the article by WIRED FOR QUALITY: The Intersection of Health IT and Healthcare Quality, Number 8, MARCH 2008. You are ...

Go to the webliography source for the national cancer

Go to the Webliography source for the National Cancer Institute's Surveillance, Epidemiology, and End Results (SEER) Program. In the Fast Stats, create your own cancer statistical report, "Stratified by Data Type," and u ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As