Using the following project information:
Activity Optimistic Time
Estimate(weeks) Most Likely Time
Estimates (weeks) Pessimistic Time
Estimates (weeks) Immediate
Predecessor(s) Variance Expected Time
(weeks)
A 3 6 9 none 1.000 6.00
B 3 5 7 A 0.444 5.00
C 4 7 12 A 1.778 7.33
D 4 8 10 B 1.000 7.67
E 5 10 16 C 3.361 10.17
F 3 4 5 D,E 0.111 4.00
G 3 6 8 D,E 0.694 5.83
H 5 6 10 F 0.694 6.33
I 5 8 11 G 1.000 8.00
J 3 3 3 H,I 0.000 3.00
The critical path is A-C-E-G-I-J.
(a) Calculate the probability that the project will be completed in 38 weeks.
P(project ? 38) =
(b) Calculate the probability that the project will be completed in 42 weeks.
P(project ? 42) =
(Round your answers to 3 decimal places, the tolerance is +/-0.005.)