Ask Financial Management Expert

This week, you will have two deliverables to complete for the project. See the Course Project Overview for details.

• Using MS Project, create a project schedule (minimum of 50 project tasks) and allocate project resources-35 points

Week 3 Project Guidelines - Microsoft Project

Congratulations! You have just completed the project charter and scope statement. Now that you know what needs to be done, as the

Project Manager, you are now ready to begin planning your project schedule.

This week, you will have two deliverables to complete the assignment.

• Using MS Project, create a project schedule and align resources-35 points

Please provide one deliverable (MS Project file).

To help guide you through this assignment, please follow the three-step process below.

Step 1: Create MS Project Schedule

The following steps should be followed when setting up your Course Project with Microsoft Project 2013 or 2016.

1. Set the basic project information

o Open MS Project.

o Click on File (top left), select Save as and enter the file name as (your name) cp1. For example, SmithJanecp1.mpp.

o Click on the Project area and select Project Information. In the Project Information dialogue box, set the start date of your project.

o Leave other dates as is. Click on OK.

2. Set basic Gantt chart format (use also for tracking Gantt chart view).

o Right click on the mouse in the gray area of the Gantt chart on the right side of the screen where the dates in month and days are for the menu and select Timescale.

o In the Timescale dialogue box:

Select the Middle Tier tab set Units to Quarters.

Select the Bottom Tier tab set Units to Months.

o Click on OK.

3. Setup the default task units to weeks

o Click File, and then click Options.

o In the Project Options dialog box, click Schedule.

o Under Scheduling options in this project, set the following.

New tasks created select Auto Scheduled

Duration is entered in select Weeks

Default task type select Fixed Duration

o Click OK to close the dialog box.

4. Set up the Resource Sheet.

Once you have set the defaults, we are ready to move on. If you have not done so already, you need to create the project's work packages and activities from the Project's WBS. Once this is done, insert your project name, deliverables, work packages, and activities in the column Task Name in MS Project.

o Enter the task durations in the Duration Column.

o Enter the predecessor(s) for each task in the predecessors column. If there is no duration or predecessor listed, leave the column blank.

Note: If you do not see the Predecessors Column, move the vertical line between the Entry Form and the Gantt chart to the right to reveal the column. Click on the line and drag to move it. Columns can be expanded or contracted individually to accommodate information the same way column width is adjusted in MS Excel.

Analyze your Schedule and Network Diagram

To see the network diagram, click on View, then select Network Diagram. Activities on the Critical Path are outlined in red, while noncritical path activities are outlined in blue.

Step 2: Allocate Resources in the MS Project Schedule

Once you have the WBS created in MS Projects, you need to assign resources to each activity. Remember only assign resources to activities, not other items on the WBS. Before you can do this, you need to create a resources sheet in MS Projects. To create a Resource sheet, click on View, Resource Sheet.

Enter the Resource name, whether it is a human resource, a cost, or a material. Once this is finished, one can tie these resources to individual activities. Don't worry about costs, as that is next week's work.

To assign your resources to the aligned tasks in MS Project, follow the steps below.

Assign hourly resources and costs to the tasks that you have already entered.

• Choose View-Gantt Chart. Place active window on the first task.

• Click on the Double Headed icon on the upper tool bar (Assign Resources), or click Alt-F10.

• In the resource assignment window, select the appropriate resource for each activity.

• Repeat for all resources and activities according to the Resource List above.

Analyze Your Resource Allocation and Assignments

There are several methods to check for over-allocated resources.

1. Click on View, Resource Sheet-Resource(s) in red color are over-allocated.

2. Click on View, Resource Usage-Resource(s) in red color are over-allocated resource(s) by date.

3. Click on Project, Reports. A dialog box appears, click on Assignments then Select. Then click the report for Overallocated Resources, and then Select to print or view.

4. Remember with resources you need to assign how much time (by a percentage) each resource will be allocated to each activity. Simply lowering a given percentage may clear an over-allocation, but in real life this is not possible. One must come up with a better method do clear resource over-allocations.

Financial Management, Finance

  • Category:- Financial Management
  • Reference No.:- M92837368
  • Price:- $60

Priced at Now at $60, Verified Solution

Have any Question?


Related Questions in Financial Management

Assignment problems1 on the day harry was born his parents

Assignment Problems 1. On the day Harry was born, his parents put $1600 into an investment account that promises to pay a fixed interest rate of 5 percent per year. How much money will Harry have in this account when he ...

1 activities of a company that require the spending of cash

1) Activities of a company that require the spending of cash are known as: A) Uses of cash. B) Cash on hand. C) Cash receipts. D) Sources of cash. E) Cash collections. 2) Relationships determined from a firm's financial ...

Module discussion forumto prepare for this discussion

Module : Discussion Forum To prepare for this discussion, review "Basics of Speechwriting" and "Basics of Giving a Speech" in textbook Chapter 15. Then watch this video of Apple founder and CEO Steve Jobs giving the 2005 ...

Launching a new product linefor this portfolio project

Launching a New Product Line For this Portfolio Project Option, you will act as an employee in a large company that develops and distributes men's and women's personal care products. The company has developed a new produ ...

Question 1 discuss valuing bonds and how interest rates

Question : 1) Discuss valuing bonds and how interest rates affect their value. Also consider the importance of the yield-to-maturity (YTM). 2) Discuss common stocks and preferred stocks. Also, which common stock valuatio ...

Introductionlast week you determined the root causes of the

Introduction Last week, you determined the root cause(s) of the problem you are trying to resolve for your final paper. As a reminder, the decision you are working on is the one that you selected in week two. This week, ...

You have owned and operated a successful brick-and-mortar

You have owned and operated a successful brick-and-mortar business for several years. Due to increased competition from other retailers, you have decided to expand your operations to sell your products via the Internet. ...

You will be conducting an interview with a market research

You will be conducting an interview with a market research professional or a company representative. Use the results of your research to make specific recommendations on how market research can be applied to the Marketpl ...

Question 1 what is marketing research what are the two

Question 1: What is marketing research? What are the two primary types of research? Question 2: What factors influence marketing research? Question 3: The role of statistics in business decision-making? Assignment : Sele ...

Chapter 74 for commercial banks what is meant by a managed

Chapter 7 4. For commercial banks, what is meant by a managed liability? What role do liquid assets play on the balance sheet of commercial banks? What role do money market instruments play in the asset and liability man ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As