The city of Greendale wants to contract with your company to build a new baseball stadium. They have received a bond issue that will provide for $100M for the project. The proposal is that 5 equal payments of $20M will be paid over the course of the project. The initial investment that your company will require is $20M. The projected annual labor and materials budget is $10M. Additionally, you will need to make a capital outlay of $10M in year 3 for new equipment. The company requires a rate of return of 15%.

The stadium is an outdoor structure with a retractable roof. The project begins with clearing the site. Once the site is clear, work can start simultaneously on the structure itself and demolishing an adjacent building site. This demolition is necessary to create a construction stage for storing materials and equipment. The work on the stadium begins by driving 160 support pilings. Next comes the pouring of the lower concrete bowl. Once this is done the construction site has been set up, then the pouring of the main concourse, the installation of the playing field, and the construction of the upper steel bowl can occur.

Once the concourse and upper bowl are completed, work can start simultaneously on building the luxury boxes, installing the sets, installing the jumbotron, and installing the stadium infrastructure which includes: bathrooms, lockers, restaurants, etc. Once the seats are installed then the steel canopy can be constructed followed by the installation of the lights. The retractable roof represents the most significant technical challenge to the project.

Building the roof track supports can begin after the lower concrete bowl is constructed. At this time the dimensions of the roof can be finalized and the construction of the roof at a separate site can begin. After the roof supports are completed then the roof tracks can be installed. Once the tracks and the roof are complete then the roof can be installed and made operational. Once all activities are completed a final inspection is required prior to occupancy. For purposes of this case assume the following:

1. The following holidays are observed: January 1, Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.

2. If a holiday falls on a Saturday then Friday will be given as an extra day off and if it falls on a Sunday then Monday will be given as a day off.

3. The construction crew work Monday through Friday.

4. As soon as the bid is accepted work will begin on May 1, 2017.

5. All duration and relationship data is located in the posted spreadsheet.

Information given: TABLE 1

Greendale Baseball Stadium

ID ---------------------------------------Task Duration ---------------Predecessors

2. Clear Site ---------------------------------150 ----------------------------0

3. Demolish Building -----------------------75 -----------------------------2

4. Set up Construction Site --------------150 ----------------------------3

5. Drive support piles ----------------------250 ---------------------------2

6. Pour lower concrete bowl -------------250 ---------------------------5

7. Pour main concourse -------------------250 ---------------------------6,3

8. Installation of playing field --------------210 --------------------------6,3

9. Construction upper steel bowl --------250 ---------------------------3,6

10. Install seats -----------------------------300 ---------------------------7,9

11. Build luxury boxes ---------------------210 ---------------------------7,9

12. Install Scoreboard ---------------------75 ----------------------------7,9

13. Stadium infrastructure ----------------250 --------------------------7,9

14. Construct steel canopy ---------------175 ---------------------------10

15. Light installation ------------------------75 ---------------------------14

16. Build roof supports --------------------210 ---------------------------6

17. Construct roof --------------------------350 --------------------------16

18. Install roof tracks -----------------------210 --------------------------16

19. Install roof -------------------------------210 -------------------------17,18

20. Final inspection ------------------------ 40 ---------------------------19,15,11,13,8

PROBLEMS:

1. Perform an NPV assessment to first determine whether your company should accept the contract.

2. If you decide to proceed what is the expected NPV value of the contract.

3. Develop a scope statement for this project.

4. Then develop a work breakdown structure that reflects the information in table 1.

5. What is the expected duration of the project and assuming you will begin construction on October 1, 2016, what date do you expect to complete?

6. What is the critical path for the project?

7. Prepare a Gantt chart for the project schedule.

Financial Management, Finance

  • Category:- Financial Management
  • Reference No.:- M92370065

Have any Question?


Related Questions in Financial Management

Hedging assignment -your portfolio a stock is currently

Hedging Assignment - Your portfolio: A stock is currently trading at 55. You hold a portfolio of the following instruments: Long 200 shares of stock Long 200 puts with a strike of 50 and maturity of three months (T=13/52 ...

Personal savings strategiespart i identify all the lazy

Personal Savings Strategies Part I: Identify all the lazy dollars in your financial life. Identify source, amount and what action might be indicated. Part II. Develop a personal and household savings plan. What savings s ...

Test1 if a persons required return decreases for an

TEST 1) If a person's required return decreases for an increase in risk, that person is said to be risk-seeking. risk-indifferent. risk-adverse. risk-aware. 2) Last year Mike bought 100 shares of Dallas Corp. common stoc ...

Respond to the following questionas part of the financial

Respond to the following question: As part of the financial planning process, a common practice in the corporate finance world is restructuring through the process of mergers and acquisitions (M&A). It seems that on a re ...

Hospitality financial management hfm assignment - cvp

Hospitality Financial Management (HFM) Assignment - CVP Analysis You are assisting management consider different cost and pricing strategies. Consider the following data and report to management your findings. 1. The coc ...

Assignmentassignment purposes1 evaluate the characteristics

Assignment Assignment Purposes: 1. Evaluate the characteristics of e-commerce. 2. Demonstrate effective use of technology for communication. 3. Evaluate the effectiveness of an e-commerce Web site. 4. Explain the securit ...

Question under what circumstances are price factors more

Question : Under what circumstances are price factors more important than non-price factors during a source selection? Under what circumstances are non-price factors more important? Use headings to compare and contrast t ...

Uit analyzing and managing inventorydeliverable length

Unit: Analyzing and Managing Inventory Deliverable Length: 8-10 PowerPoint slides with speaker notes Library Research Assignment After the last report, the owners of Stone Horse Supply Company, John and Michael, have con ...

Assignment the art of negotiationresearch a current

Assignment : The Art of Negotiation Research a current conflict or negotiation in progress from the last 6 months like peace talks in the Middle East, a corporate merger, a labor dispute, etc. Write a six to eight (6-8) ...

Unit 3 dbthe president of eec recently called a meeting to

Unit 3 DB The President of EEC recently called a meeting to announce that one of the firm's largest suppliers of component parts has approached EEC about a possible purchase of the supplier. The President has requested t ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As