Tasks 1 The failure history for rollers supporting a production-line conveyor belt has been analysed. There are 8 such rollers on this critical unit (positions 1 - 8).

The policy is to replace all of these rollers at the overhaul of the conveyor, under contract. The overhaul is conducted once per year. Failures between overhauls are replaced by the operating department personnel. Failure data has been collected over a 3 year period with special attention to the recording of the age of the rollers when they were replaced

A total of 15 rollers were changed during that time and the analysis indicates that the individual roller reliability can be modelled with a Weibull distribution with shape parameter 3.8, scale parameter 115 days and location parameter 255 days. Rollers can only be changed when the system is stopped.

Access to all of the rollers is obtained by removing guarding from around the conveyor and the conveyor belt itself. Following this work, all rollers are accessible. This takes 1 hour. Each roller requires a further 15 minutes to change. Replacement of the belt and guarding takes a further 1 1/2 hours due to the need to accurately realign a sensitive thickness sensor used to control product quality during processing.

Material and labour costs to change one roller amounts to A$1100 per roller, irrespective of the time taken. In addition, it has been calculated that due to the disruption caused to the system, unplanned stops have a fixed delay cost of A$8500 and an additional cost of A$3900 per hour for every hour the system is down. Planned stops incur a cost of A$4000 per hour.

1. Which renewal strategy best represents the current approach being applied to the roller maintenance:
a. Age replacement of individual rollers.
b. Block replacement of individual rollers.
c. Age replacement of the 8 rollers treated as a single component d. Replacement on failure of the 8 rollers treated as a single component? Explain the reasoning behind your answer.

2. Calculate the cost of preventive renewal and the cost of renewal on failure per roller for each of the 4 renewal strategies listed in Q1.

3. Undertaking quantitative analysis, as required, determine whether the current renewal strategy is acceptable. Suggest alternatives if appropriate and substantiate your suggestions. Your answer should include consideration of the 4 strategies identified in Q1. 2 Condition monitoring of the rollers is being investigated. Two options are being considered. The first involves installing permanent accelerometers and connecting these to a remote test point to allow inspection during operation.

The cost of inspection would be $100 and the likelihood of successful detection of incipient failure would be 0.99. It is considered the inspection would provide a warning time between 10 days and 55 days giving a Weibull warning time distribution with shape parameter 3.44, scale parameter 25 days and location parameter 10 days.

What annual saving would ENGG960/MECH487 - Maintenance Requirements Analysis © UOW/P.Gordon/R.Dwight Page 6 this option achieve in comparison to the optimum usage based renewal strategy.

3 The second option involves continuous remote monitoring of the accelerometers. This option it is believed would achieve 100% likelihood of successful detection of incipient failure with no additional inspection costs. What annual saving would this option achieve in comparison to the optimum usage based renewal strategy?

1000 words 2 harvard references

Attachment:- Assignment.rar

Basic Finance, Finance

  • Category:- Basic Finance
  • Reference No.:- M91978869
  • Price:- $40

Guranteed 36 Hours Delivery, In Price:- $40

Have any Question?


Related Questions in Basic Finance

Briefly summarize the partnership business structure and

Briefly summarize the partnership business structure and the equity rights partners have, both in the context of managerial rights and ownership.

Assignment - valuing a leveraged firma firm is planning to

Assignment - Valuing a leveraged firm A firm is planning to take a project that if funded entirely with equity has net after tax cash flows as indicated in the table below. Year Cash flow 0 -15000000 1 2000000 2 2000000 ...

What are financial ratios commonly used in quantitative

What are financial ratios commonly used in quantitative models of debt ratings? List THREE financial ratios that represent three different factors and explain why these ratios can capture the company's ability to meet it ...

A firm recently paid a 044 annual dividend the dividend is

A firm recently paid a $0.44 annual dividend. The dividend is expected to increase by 10 percent in each of the next four years. In the fourth year, the stock price is expected to be $20. If the required return for this ...

If you insulate your office for 16000 you will save 1600 a

If you insulate your office for $16,000, you will save $1,600 a year in heating expenses. These savings will last forever. a.  What is the NPV of the investment when the cost of capital is 5%? 10%? b.  What is the IRR of ...

Market-value ratios garret industries has a priceearnings

(?Market-value ratios?) Garret Industries has a? price/earnings ratio of 19.46X a. If? Garret's earnings per share is ?$1.65?, what is the price per share of? Garret's stock? b. Using the price per share you found in par ...

Youre prepared to make monthly payments of 210 beginning at

You're prepared to make monthly payments of $210, beginning at the end of this month, into an account that pays 6.2 percent interest compounded monthly. How many payments will you have made when your account balance reac ...

Question - we bought a stock for 4585 four years ago and we

Question - We bought a stock for $45.85 four years ago and we can sell it for $59.13 today. The stock does not pay dividends. What annual rate of return have we earned?

A bank makes a loan on 01012010 with the following

A bank makes a loan on 01/01/2010 with the following payments: 06/30/2010 - $2,300,000 12/31/2010 - $1,300,000 06/30/2011 - $5,700,000 12/31/2011 - $3,400,000 06/30/2012 - $360,000 12/31/2012 - $560,000 At an annual rate ...

Suppose that a zero-coupon bond that matures in 1 year

Suppose that a zero-coupon bond that matures in 1 year costs $97 and that a zero-coupon bond that matures in 2 years costs $94. a) What must be the price of a 2-year coupon bond with a 5% coupon rate? (All face values ar ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As