Read the case study on page 494 of the textbook entitled “Southwestern University Stadium Construction” (Shown Below). As you read the Case Study, take notes on how the concepts of Project Management can lead you to develop effective solutions to the three associated Discussion Questions.

Southwestern University

After 6 months of study, much political arm wrestling, and some serious financial analysis, Dr. Martín Starr, president of Southwestern University, had reached a decision. To the delight of its students, and to the disappointment of its athletic boosters, SWU would not be relocating to a new football site, but would expand the capacity at its on-campus stadium.

Adding 21,000 seats, including dozens of luxury skyboxes, would not please everyone. The influential football coach, Bo Pitterno, had long argued the need for a first-class stadium, one with built-in dormitory rooms for his players and a palatial office appropriate for the coach of a future NCAA champion team. But the decision was made, and everyone, including the coach, would learn to live with it.

The job now was to get construction going immediately after the 2001 season ended. This would allow exactly 270 days until the 2002 season opening game. The contractor, Hill Construction (Bob Hill being an alumnus, of course), signed his contract. Bob Hill looked at the tasks his engineers had outlined and looked President Starr in the eye, "I guarantee the team will be able to take the field on schedule next year," he said with a sense of confidence. "I sure hope so," replied Starr. "The contract penalty of $ 10,000 per day for running late is nothing compared to what Coach Pitterno will do to you if our opening game with Penn State is delayed or canceled." Hill, sweating slightly, did not need to respond. In football-crazy Texas, Hill Construction would be mud if the 270-day target were missed.

Back in his office, Hill again reviewed the data (see Table 12.11 and note that optimistic time estimates can be used as crash times). He then gathered his foremen. "Boys, if we're not 75% sure we'll finish this stadium in less than 270 days, I want this project crashed! Give me the cost figures for a target date of 250 days— also for 240 days. I want to be early, not just on time!"

Questions

1. Develop a network drawing for Hill Construction and determine the critical path. How long is the project expected to take?

2. What is the probability of finishing in 270 days?

3. If it is necessary to crash to 250 or 240 days, how would Hill do so, and at what costs? As noted in the case, assume that optimistic time estimates can be used as crash times.

Financial Management, Finance

  • Category:- Financial Management
  • Reference No.:- M91418097

Have any Question?


Related Questions in Financial Management

Assignment problems1 on the day harry was born his parents

Assignment Problems 1. On the day Harry was born, his parents put $1600 into an investment account that promises to pay a fixed interest rate of 5 percent per year. How much money will Harry have in this account when he ...

1 activities of a company that require the spending of cash

1) Activities of a company that require the spending of cash are known as: A) Uses of cash. B) Cash on hand. C) Cash receipts. D) Sources of cash. E) Cash collections. 2) Relationships determined from a firm's financial ...

Module discussion forumto prepare for this discussion

Module : Discussion Forum To prepare for this discussion, review "Basics of Speechwriting" and "Basics of Giving a Speech" in textbook Chapter 15. Then watch this video of Apple founder and CEO Steve Jobs giving the 2005 ...

Launching a new product linefor this portfolio project

Launching a New Product Line For this Portfolio Project Option, you will act as an employee in a large company that develops and distributes men's and women's personal care products. The company has developed a new produ ...

Question 1 discuss valuing bonds and how interest rates

Question : 1) Discuss valuing bonds and how interest rates affect their value. Also consider the importance of the yield-to-maturity (YTM). 2) Discuss common stocks and preferred stocks. Also, which common stock valuatio ...

Introductionlast week you determined the root causes of the

Introduction Last week, you determined the root cause(s) of the problem you are trying to resolve for your final paper. As a reminder, the decision you are working on is the one that you selected in week two. This week, ...

You have owned and operated a successful brick-and-mortar

You have owned and operated a successful brick-and-mortar business for several years. Due to increased competition from other retailers, you have decided to expand your operations to sell your products via the Internet. ...

You will be conducting an interview with a market research

You will be conducting an interview with a market research professional or a company representative. Use the results of your research to make specific recommendations on how market research can be applied to the Marketpl ...

Question 1 what is marketing research what are the two

Question 1: What is marketing research? What are the two primary types of research? Question 2: What factors influence marketing research? Question 3: The role of statistics in business decision-making? Assignment : Sele ...

Chapter 74 for commercial banks what is meant by a managed

Chapter 7 4. For commercial banks, what is meant by a managed liability? What role do liquid assets play on the balance sheet of commercial banks? What role do money market instruments play in the asset and liability man ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As