Question: The Ventron Engineering Company has just been awarded a $2 million development contract by the U.S. Army Aviation Systems Command to develop a blade spar for its Heavy Lift Helicopter program. The blade spar is a metal tube that runs the length of and provides strength to the helicopter blade. Due to the unusual length and size of the Heavy Lift Helicopter blade, Ventron is unable to produce a single-piece blade spar of the required dimensions using existing extrusion equipment and material. The engineering department has prepared two alternatives for developing the blade spar:

(1) sectioning or

(2) an improved extrusion process.

Ventron must decide which process to use. (Backing out of the contract at any point is not an option.) The risk report has been prepared by the engineering department. The information from this report is explained next. The sectioning option involves joining several shorter lengths of extruded metal into a blade spar of sufficient length. This work will require extensive testing and rework over a 12-month period at a total cost of $1.8 million. Although this process will definitely produce an adequate blade spar, it merely represents an extension of existing technology. To improve the extrusion process, on the other hand, it will be necessary to perform two steps:

(1) improve the material used, at a cost of $300,000, and

(2) modify the extrusion press, at a cost of $960,000.

The first step will require six months of work, and if this first step is successful, the second step will require another six months of work. If both steps are successful, the blade spar will be available at that time, that is, a year from now. The engineers estimate that the probabilities of succeeding in steps 1 and 2 are 0.9 and 0.75, respectively. However, if either step is unsuccessful (which will be known only in six months for step 1 and in a year for step (2), Ventron will have no alternative but to switch to the sectioning process-and incur the sectioning cost on top of any costs already incurred. Development of the blade spar must be completed within 18 months to avoid holding up the rest of the contract. If necessary, the sectioning work can be done on an accelerated basis in a six-month period, but the cost of sectioning will then increase from $1.8 million to $2.4 million. The director of engineering, Dr. Smith, wants to try developing the improved extrusion process. He reasons that this is not only cheaper (if successful) for the current project, but its expected side benefits for future projects could be sizable. Although these side benefits are difficult to gauge, Dr. Smith's best guess is an additional $2 million. (These side benefits are obtained only if both steps of the modified extrusion process are completed successfully.)

a. Develop a decision tree to maximize Ventron's EMV. This includes the revenue from this project, the side benefits (if applicable) from an improved extrusion process, and relevant costs. You don't need to worry about the time value of money; that is, no discounting or net present values are required. Summarize your findings in words in the spreadsheet.

b. What value of side benefits would make Ventron indifferent between the two alternatives?

c. How much would Ventron be willing to pay, right now, for perfect information about both steps of the improved extrusion process? (This information would tell Ventron, right now, the ultimate success or failure outcomes of both steps.)

Statistics and Probability, Statistics

  • Category:- Statistics and Probability
  • Reference No.:- M92450807
  • Price:- $15

Priced at Now at $15, Verified Solution

Have any Question?


Related Questions in Statistics and Probability

Arvo corporation is trying to choose between three

Arvo Corporation is trying to choose between three alternative investments. The three securities that the company is considering are as follows: Tax-free municipal bonds with a return of 8.8%. Wooli Corporation bonds wit ...

Want the 98 confidence interval when the sample size is 50

Want the 98% confidence interval when the sample size is 50, sample mean is 42 and sample standard deviation is 5. Keep three decimal places in your response.

The glen arboretum wants to start removing invasive norway

The Glen arboretum wants to start removing invasive Norway Maple trees. To determine just how bad the problem is you set up five plots that are three meters on each side. You find that your plots have 2, 5, 9, 1, and 3 N ...

Note you will be limited to no more than 3 attempts for

(NOTE: You will be limited to no more than 3 attempts for credit on this problem.) Rework problem 23 from section 4.1 of your text involving a basketball player's three point shooting. Assume that his shots are Bernoulli ...

The time to complete 1 construction project for company a

The time to complete 1 construction project for company A is exponentially distributed with a mean of 1 year. Therefore: (a) What is the probability that a project will be finished in one and half years? (b) What is the ...

Iq test scores of students are normally distributed with

IQ test scores of students are normally distributed with mean μ=100 and standard deviation σ=10. What is the 33th percentile of the IQ scores? For a randomly chosen student, what is the probability that his or her IQ sco ...

A social psychologist recently developed a childhood

A social psychologist recently developed a childhood memories test that is intended to measure how people recall pleasant and unpleasant memories from childhood. Scores on this test range from 1 (very unpleasant) to 100 ...

A researcher is planning to a silvicultural study using 3

A researcher is planning to a silvicultural study using 3 different fertilizers on 3 adjacent plots. How many ways can the 3 plots be arranged if there are 18 fertilizers to choose from?

A student must answer 6 multiple choice questions for a

A student must answer 6 multiple choice questions for a test, but the student did not study well. There are 6 answers per question, but only one is correct. If the student randomly guesses on each questions, what is the ...

1 this table summarizes the results from

1) This table summarizes the results from along+termrandomized clinicaltrial to  determine whether aspirin reduces the risk of heart attack. Researchers  randomly assigned a large sample of healthy male physicians (22,07 ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As