The BUS670 Company has for projects to complete and four workers with varying degree os expertise for each project. Estimates of process time (in hours) for each project by each worker are shown below. Development time costs an average of $200 per hour. Assign each worker to a project so that cost is minimized.

Worker Project 1 Project 2 Project 3 Project 4
Bryan 20 10 12 20
Kari 12 4 8 12
Noah 14 12 10 12
Chris 18 10 8 20

Part 1a If management wishes to schedule workers with specific projects that minimizes total cost and gets all projects done, what would that minimized cost be?

Part 1b Which project should be assigned to which worker for minimizing the total cost?

Q2 Scheduling

Car Washing Waxing
1 10 10
2 3 2
3 7 5
4 8 6
5 5 5

The local car wash has five cars waiting to be washed and waxed. The time required in minutes for each activity is given below.

Part 2a In what order should the cars be processed through the facility that is the most efficient overall?

Part 2b How long from start to finish will it take to complete the processing the five cars?

Part 2c How much idle time was incurred by the washing process?

Part 2d How much idle time was incurred by the waxing process?

Q3 Forecasting

Suppose today is May 16, 2014 and the data below are the historical sales figures for the BUS670 company for the last few years.

Part 1 -- Forecast the weekly sales for the next 52 weeks and put these values in cells B174 through B225 below.

Part 2 -- How many more or fewer sales will the forecasted 52 weeks have over the prior 52 weeks?

Part 3 -- Which forecasted week is expected to have the greatest sales volume?

Part 4 -- Which forecasted week is expected to have the lowest sales volume?

Q4 Consulting

Part 1 -- Project Consulting

Please refer to the four PowerPoint documents. These are actual analyses produced about specific companies. Please select ONE of these 4 presentations and in a Word document, please provide detailed suggestions to the authors of the material that would improve the quality of the content, as though you were the teacher grading the material. The comments should be of value, and not cosmetic or immaterial, such as wording suggestions, number of pages or length suggestions, etc., but instead should be focused on crisp, clear, and concise recommendations that would increase the value the output. For the sake of this question, suppose this project was scored a C. Please list all the recommedations that would make it an A+.

Part 2 -- BusinessConsulting

Refering to the same PowerPoint project you addressed in part 1 above, in a Word document, please provide a critique of this document from a BUSINESS CONSULTING perspective. For this question, your comments about about business implications, recommendations, and your thoughts of the project as it relates to business issues. If you think there is a poingnat point that was not made in the PowerPout but should have been, that is a comment about content that you should list here. If they never discussed the impact of a certain element of the business, or perhaps did not mention the impact on the product, pricing, customer, comeptitor, workers, etc. these are comments woth making. If the recommendations they made do not help the business but instead you have a better recommendation stemming from the material that could aid the business, then that is a comment you should produce. You are not critiquing the PowerPoint from an teacher point of view here. You are critiquing it from a BUSINESS CONSULTING point of view. Please pick the same one PowerPoint document for part 1 and part 2 and provide whatever obserations, comments, etc that themselves add value.


Attachment:- ASTAT_Question.xlsx

Applied Statistics, Statistics

  • Category:- Applied Statistics
  • Reference No.:- M9895221
  • Price:- $50

Priced at Now at $50, Verified Solution

Have any Question?


Related Questions in Applied Statistics

Question 1 for the prostate data set fit a model with lpsa

Question 1. For the prostate data set, fit a model with lpsa as the response, and the other variables as predictors. (a) Suppose a new patient with the following values arrives: lcavol = 1.45000, lweight = 3.59801, age = ...

Part a -question 1 - an analyst considers to test the order

PART A - Question 1 - An analyst considers to test the order of integration of some time series data. She decides to use the DF test. She estimates a regression of the form Δy t = μ + ψy t-1 + u t and obtains the estimat ...

Business statistics assignment -quiz 1 -question 1 - a

Business Statistics Assignment - Quiz 1 - Question 1 - A study is under way in the Otway National Park to determine the mature height of Mountain Ash gum trees. Specifically, the study is attempting to determine what fac ...

Assignment - research topicpurpose the purpose of this task

Assignment - Research topic Purpose: The purpose of this task is to ensure you are progressing satisfactorily with your research project, and that you have clean, useable data to analyse for your final project report. Ta ...

Assessment task -you become interested in the non-skeletal

Assessment Task - You become interested in the non-skeletal effects of vitamin D and review the literature. On the basis of your reading you find that there is some evidence to suggest that vitamin D deficiency is linked ...

A company produces labeled packaging material and the

A company produces labeled packaging material and the company intends to buy a new machine for shaping and labeling. The company has been approached by two different companies and the production manager did a test on the ...

Question - go to the website national quality forum nqf

Question - Go to the website, National Quality Forum (NQF), located in the Webliography, and download the article by WIRED FOR QUALITY: The Intersection of Health IT and Healthcare Quality, Number 8, MARCH 2008. You are ...

Assignment -in this assignment ms excel must be used to

Assignment - In this assignment MS Excel must be used to perform any calculations/graphical presentations as required in this assignment. Question 1 - Below you are given the examination scores of 20 students (data set a ...

Using minitab to construct linear regression modelsscatter

Using Minitab to Construct Linear Regression Models Scatter Plot To obtain a simple scatter plot using Minitab: One of the first steps in the analysis of the study data is to create a scatter plot that compares the quant ...

Business analytics and statistics research reportthis

Business Analytics and Statistics Research Report This assignment is based on fictional data. You are creating a business report for the CEO of a retail company called, Athlete Panda. It must be professional in presentat ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As