Q1) Miracle Marketing has received construct from a large pharmaceutical firm to design nationwide advertising campaign for their recently approved cancer drug. Drug is easily taken, compared with present intravenous drugs, and can be administered from home. Miracle Marketing has alloted to task a project manager who, in turns has delegated minor subprojects to subordinate managers.
Project was estimated by using ADM/PERT analysis. Due to extensive length of project many activities were combined; Following is the result.
Activity
|
Time(month)
|
AB
|
3
|
BC
|
6
|
BD
|
2
|
BF
|
5
|
BE
|
4
|
CD
|
9
|
DG
|
20
|
FG
|
6
|
EH
|
11
|
EI
|
19
|
GJ
|
1
|
HK
|
3
|
IL
|
9
|
LM
|
12
|
KN
|
7
|
JO
|
4
|
MN
|
15
|
NP
|
13
|
OP
|
10
|
Determine the critical path and expected completion date.