PERT Network Diagram 1 illustrates the ten interrelated activities that comprise a certain project.

PERT Network Diagram 1

976_pert 1.png

The information presented in Table 1 represents the optimistic activity time (a), most probable activity time (m), and pessimistic activity time (b) in weeks for each activity associated with the project.

Activity

Optimistic (a)

Most Probable (m)

Pessimistic (b)

A

2

3

4

B

1

3

5

C

2

5

8

D

1

2

3

E

2

4

6

F

1

3

5

G

2

4

6

H

1

3

5

I

2

4

6

J

1

4

7

 

2084_pert 2.png

1. Using the information provided in Table 1, calculate the expected activity time (t) in weeks for each activity and then enter this information in the appropriate data field provided for each activity in PERT Network Diagram 2 in order to complete this diagram. What is the expected activity time in weeks for each of the ten activities? (Arrange your answers in alphabetical order by activity beginning with activity A and ending with activity J).

2. Using the information provided in Table 1, calculate the variance for the estimated activity time for each activity. (Arrange your answers in alphabetical order by activity beginning with activity A and ending with activity J).

3. Using the information in completed PERT Network Diagram 2, calculate the overall estimated activity time in weeks for each path through the network; identify which path constitutes the critical path.

4. Using the information provided in Table 1, calculate the standard deviation for the project.

5. Using the information provided in Table 1 and completed Project Network Diagram 2, calculate the probability of the project critical path activities being completed in less than or equal to 24 weeks.

The information presented in Table 2 represents the calculated Earliest Start, Earliest Finish, Latest Start and Latest Finish times for each activity.

Table 2

Activity

Earliest Start

Earliest Finish

Latest Start

Latest Finish

A

0

3

0

3

B

3

6

3

6

C

6

11

6

11

D

11

13

16

18

E

6

10

7

11

F

11

14

11

14

G

18

22

18

22

H

0

3

7

10

I

3

7

10

14

J

14

18

14

18

1.      Using the information provided in Table 2, calculate the slack time in weeks for each activity.  (Arrange your answers in alphabetical order by activity beginning with activity A and ending with activity J).

The information presented in Table 3 represents the total budgeted cost for each activity associated with the project. 

Activity

Total Budgeted Cost

A

$22,000

B

$30,000

C

$24,000

D

$8,000

E

$7,000

F

$9,000

G

$10,000

H

$12,000

I

$23,000

J

$11,000

2.      Using the information provided in Table 2 and Table 3, calculate the budgeted costs for week seven of the project based upon using the Earliest Start Date for each activity and calculate the budgeted costs for week seven of the project based upon using the Latest Start Date for each activity in order to then calculate the difference in the cashflow for week seven between these two scenarios.

3.      Using the information provided in Table 2 and Table 3, calculate the budgeted costs for week eighteen of the project based upon using the Earliest Start Date for each activity and calculate the budgeted costs for week eighteen of the project based upon using the Latest Start Date for each activity in order to then calculate the difference in the cashflow for week eighteen between these two scenarios.

Table 4 represents the percentage of completion and actual cost of work performed data for each activity associated with the project at a certain point in time during the project.


Activity

Total Budgeted Cost

Percent of Completion

Actual Cost of Work Completed

A

$22,000

100%

$23,000

B

$30,000

100%

$28,000

C

$24,000

100%

$27,500

D

$8,000

85%

$7,300

E

$7,000

65%

$9,800

F

$9,000

0%

$0

G

$10,000

0%

$0

H

$12,000

45%

$5,100

I

$23,000

0%

$0

J

$11,000

0%

$0

4.      Using the information provided in Table 4, calculate the value of work completed and activity difference for each activity.  Which activity evidences the single largest activity difference (regardless of whether it is a cost overrun or cost underrun) at this particular point in the project?

5.      Using the information provided in Table 4, calculate the overall cost overrun or cost underrun for the project at this particular point in the project.

Table 5 represents the estimated crash time in weeks and associated total crash cost for each activity. 

 

 

Activity

Crash Time

(Weeks)

Total Crash Cost

A

2

$25,000

B

2

$40,000

C

4

$27,000

D

1

$9,000

E

3

$8,500

F

2

$12,000

G

3

$11,000

H

2

$15,000

I

3

$26,000

J

3

$13,000

6.      Using the information in completed PERT Network Diagram 2 and Table 5, crash the network in order to reduce the estimated project duration to 20 weeks while minimizing the overall crash cost. Which critical path activity would be the most logical choice for the first activity to crash?

7.      Which critical path activity would be the most logical choice for the second activity to crash?

8.      What is the total estimated cost associated with crashing the network to reduce the estimated project duration to 20 weeks at the lowest possible overall crash cost?

9.      After successfully crashing the network to reduce the estimated project duration to 20 weeks, which path through the crashed network constitutes the critical path?

Financial Management, Finance

  • Category:- Financial Management
  • Reference No.:- M91509304
  • Price:- $30

Priced at Now at $30, Verified Solution

Have any Question?


Related Questions in Financial Management

Question spirituality is a fundamental and universal

Question : Spirituality is a fundamental and universal aspect of human existence and is a critical component in working with clients, groups, communities, etc. There is a vast diversity in spiritual beliefs and religious ...

Please respond to the following discussion not an essay

Please respond to the following: {Discussion, NOT an Essay. Under 350 WORDS} a) Propose three reforms to the investment markets that might reduce their exposure to systematic risk. Support your proposals with examples. b ...

Management control systems and national cultures and

Management Control Systems and National Cultures and Corporate Social Responsibility o What steps, if any, is Amazon taking to be sensitive to the national culture. o What is Amazon doing with regard to Corporate Social ...

Respond to the following questionas part of the financial

Respond to the following question: As part of the financial planning process, a common practice in the corporate finance world is restructuring through the process of mergers and acquisitions (M&A). It seems that on a re ...

Purpose of assignmentthis assignment situates students in

Purpose of Assignment This assignment situates students in the role of a consulting team for Best Game Productions. As a team, students analyze the culture, values, and ethics of Best Game Productions and each department ...

As you have read and researched web analytics is used

As you have read and researched, web analytics is used extensively in higher education. Continue to research and source at least 5 different ways how web analytics is used by higher education institutions. You must provi ...

Consider two companies united states steel x and facebook

Consider two companies: United States Steel (X) and Facebook (FB). Look at the profiles (financial statements for 2016) of each on yahoo finance and discuss the followings (you need to calculate these values yourself and ...

Case analysis questions1 explain in 175 words what makes a

Case Analysis Questions 1. Explain in 175 words what makes a company a “multinational corporation”. 2. Complete the chart in a total of 350 words using 3 to 5 examples of multinational corporations. 3. Reading through th ...

Assignmentnow that you have gained an understanding of red

Assignment Now that you have gained an understanding of Red Carpet, Leroy has asked you to join in on a preliminary meeting with the VP of HR and other members of the organization to discuss change. The meeting was very ...

1 comparative advantagethe following chart represents the

1. Comparative Advantage The following chart represents the production capabilities of the US and Japan:.   Output per worker- day   Country Food Clothing US 2 1 Japan 3 9 a) Which country has an absolute advantage in fo ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As