PERT Network Diagram 1 illustrates the ten interrelated activities that comprise a certain project.

PERT Network Diagram 1

976_pert 1.png

The information presented in Table 1 represents the optimistic activity time (a), most probable activity time (m), and pessimistic activity time (b) in weeks for each activity associated with the project.

Activity

Optimistic (a)

Most Probable (m)

Pessimistic (b)

A

2

3

4

B

1

3

5

C

2

5

8

D

1

2

3

E

2

4

6

F

1

3

5

G

2

4

6

H

1

3

5

I

2

4

6

J

1

4

7

 

2084_pert 2.png

1. Using the information provided in Table 1, calculate the expected activity time (t) in weeks for each activity and then enter this information in the appropriate data field provided for each activity in PERT Network Diagram 2 in order to complete this diagram. What is the expected activity time in weeks for each of the ten activities? (Arrange your answers in alphabetical order by activity beginning with activity A and ending with activity J).

2. Using the information provided in Table 1, calculate the variance for the estimated activity time for each activity. (Arrange your answers in alphabetical order by activity beginning with activity A and ending with activity J).

3. Using the information in completed PERT Network Diagram 2, calculate the overall estimated activity time in weeks for each path through the network; identify which path constitutes the critical path.

4. Using the information provided in Table 1, calculate the standard deviation for the project.

5. Using the information provided in Table 1 and completed Project Network Diagram 2, calculate the probability of the project critical path activities being completed in less than or equal to 24 weeks.

The information presented in Table 2 represents the calculated Earliest Start, Earliest Finish, Latest Start and Latest Finish times for each activity.

Table 2

Activity

Earliest Start

Earliest Finish

Latest Start

Latest Finish

A

0

3

0

3

B

3

6

3

6

C

6

11

6

11

D

11

13

16

18

E

6

10

7

11

F

11

14

11

14

G

18

22

18

22

H

0

3

7

10

I

3

7

10

14

J

14

18

14

18

1.      Using the information provided in Table 2, calculate the slack time in weeks for each activity.  (Arrange your answers in alphabetical order by activity beginning with activity A and ending with activity J).

The information presented in Table 3 represents the total budgeted cost for each activity associated with the project. 

Activity

Total Budgeted Cost

A

$22,000

B

$30,000

C

$24,000

D

$8,000

E

$7,000

F

$9,000

G

$10,000

H

$12,000

I

$23,000

J

$11,000

2.      Using the information provided in Table 2 and Table 3, calculate the budgeted costs for week seven of the project based upon using the Earliest Start Date for each activity and calculate the budgeted costs for week seven of the project based upon using the Latest Start Date for each activity in order to then calculate the difference in the cashflow for week seven between these two scenarios.

3.      Using the information provided in Table 2 and Table 3, calculate the budgeted costs for week eighteen of the project based upon using the Earliest Start Date for each activity and calculate the budgeted costs for week eighteen of the project based upon using the Latest Start Date for each activity in order to then calculate the difference in the cashflow for week eighteen between these two scenarios.

Table 4 represents the percentage of completion and actual cost of work performed data for each activity associated with the project at a certain point in time during the project.


Activity

Total Budgeted Cost

Percent of Completion

Actual Cost of Work Completed

A

$22,000

100%

$23,000

B

$30,000

100%

$28,000

C

$24,000

100%

$27,500

D

$8,000

85%

$7,300

E

$7,000

65%

$9,800

F

$9,000

0%

$0

G

$10,000

0%

$0

H

$12,000

45%

$5,100

I

$23,000

0%

$0

J

$11,000

0%

$0

4.      Using the information provided in Table 4, calculate the value of work completed and activity difference for each activity.  Which activity evidences the single largest activity difference (regardless of whether it is a cost overrun or cost underrun) at this particular point in the project?

5.      Using the information provided in Table 4, calculate the overall cost overrun or cost underrun for the project at this particular point in the project.

Table 5 represents the estimated crash time in weeks and associated total crash cost for each activity. 

 

 

Activity

Crash Time

(Weeks)

Total Crash Cost

A

2

$25,000

B

2

$40,000

C

4

$27,000

D

1

$9,000

E

3

$8,500

F

2

$12,000

G

3

$11,000

H

2

$15,000

I

3

$26,000

J

3

$13,000

6.      Using the information in completed PERT Network Diagram 2 and Table 5, crash the network in order to reduce the estimated project duration to 20 weeks while minimizing the overall crash cost. Which critical path activity would be the most logical choice for the first activity to crash?

7.      Which critical path activity would be the most logical choice for the second activity to crash?

8.      What is the total estimated cost associated with crashing the network to reduce the estimated project duration to 20 weeks at the lowest possible overall crash cost?

9.      After successfully crashing the network to reduce the estimated project duration to 20 weeks, which path through the crashed network constitutes the critical path?

Financial Management, Finance

  • Category:- Financial Management
  • Reference No.:- M91509304
  • Price:- $30

Priced at Now at $30, Verified Solution

Have any Question?


Related Questions in Financial Management

Assignment problems1 on the day harry was born his parents

Assignment Problems 1. On the day Harry was born, his parents put $1600 into an investment account that promises to pay a fixed interest rate of 5 percent per year. How much money will Harry have in this account when he ...

1 activities of a company that require the spending of cash

1) Activities of a company that require the spending of cash are known as: A) Uses of cash. B) Cash on hand. C) Cash receipts. D) Sources of cash. E) Cash collections. 2) Relationships determined from a firm's financial ...

Module discussion forumto prepare for this discussion

Module : Discussion Forum To prepare for this discussion, review "Basics of Speechwriting" and "Basics of Giving a Speech" in textbook Chapter 15. Then watch this video of Apple founder and CEO Steve Jobs giving the 2005 ...

Launching a new product linefor this portfolio project

Launching a New Product Line For this Portfolio Project Option, you will act as an employee in a large company that develops and distributes men's and women's personal care products. The company has developed a new produ ...

Question 1 discuss valuing bonds and how interest rates

Question : 1) Discuss valuing bonds and how interest rates affect their value. Also consider the importance of the yield-to-maturity (YTM). 2) Discuss common stocks and preferred stocks. Also, which common stock valuatio ...

Introductionlast week you determined the root causes of the

Introduction Last week, you determined the root cause(s) of the problem you are trying to resolve for your final paper. As a reminder, the decision you are working on is the one that you selected in week two. This week, ...

You have owned and operated a successful brick-and-mortar

You have owned and operated a successful brick-and-mortar business for several years. Due to increased competition from other retailers, you have decided to expand your operations to sell your products via the Internet. ...

You will be conducting an interview with a market research

You will be conducting an interview with a market research professional or a company representative. Use the results of your research to make specific recommendations on how market research can be applied to the Marketpl ...

Question 1 what is marketing research what are the two

Question 1: What is marketing research? What are the two primary types of research? Question 2: What factors influence marketing research? Question 3: The role of statistics in business decision-making? Assignment : Sele ...

Chapter 74 for commercial banks what is meant by a managed

Chapter 7 4. For commercial banks, what is meant by a managed liability? What role do liquid assets play on the balance sheet of commercial banks? What role do money market instruments play in the asset and liability man ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As