Q1) Senior MIS design class project team has developed following schedule of activities for their project, by using their best evaluate of completion times. Both written and oral reports are required. Design the project network. Find out the critical path.
|
Activity
|
Time
|
Immediate Predecessor
|
|
A. Find client
|
4
|
---
|
|
B. Write prospectus
|
2
|
A
|
|
C. Obtain approval from client and professor
|
3
|
B
|
|
D. Complete programming
|
12
|
C
|
|
E. Do industry background research
|
10
|
---
|
|
F. Write final paper
|
6
|
D, E
|
|
G. Write oral report
|
5
|
D, E
|
i) In optimal solution, determinethe critical path?
ii) How long will it take to complete the project?