Q1) Following network is compressed representation of prospectus of start-up firm which plans to develop new, bio-electronic computer chip.
Note that 4 activities, biological elements, can start immediately.
Find:
a) Critical path.
b) Earliest time to complete the project.
c) Slack on activities E, F, and H.