Q1) In web site development project network, shows in following figure, number alongside each activity designates the activity duration (TE) in weeks.
Find out:
a) The ES and LS for each activity.
b) The earliest time that the web site can be completed
c) The slack on all activities.
d) The critical activities.
e) The critical path.