Determine the total estimated cost at completion and estimated cost to complete for the project in Problem 6, assuming the cost performance index remains the same through the remainder of the job.
In Problem 6, the actual cost of the work performed at the end of the third week for the project in Problem 4 is $16,500. Determine the cost performance index for the project.
IN PROBLEM 4, A project consists of six tasks. Task A is scheduled to begin at the start of Week 1 and finish at the end of Week 4. Task B is scheduled to begin at the start of Week 1 and finish at the end of Week 2. Task C is scheduled to begin at the start of Week 3 and end at the end of Week 4. Task D is scheduled to begin at the start of Week 1 and end at the end of Week 1. Task E is scheduled to begin at the start of Week 2 and end at the end of Week 4. Task F is scheduled to begin at the start of Week 4 and end at the end of Week 4. The budgeted cost for Task A is $10,000, for Task B is $2,000, for Task C is $3,000, for Task D is $1,000, for Task E is $6,000, and for Task F is $4,000. At the end of the third week Task A is 80% complete, Task B is 100% complete, Task C is 40% complete, Task D is 100% complete, Task E is 55% complete, and Task F has not started. What is the schedule performance index for the project at the end of the third week?

Basic Finance, Finance

  • Category:- Basic Finance
  • Reference No.:- M91893005
  • Price:- $10

Priced at Now at $10, Verified Solution

Have any Question?


Related Questions in Basic Finance

1 brandon has partial amnesia and forgot how much he

1.) Brandon has partial amnesia and forgot how much he borrowed. He does remember that he borrowed the money 21 months ago and that the interest rate was 5% per annum. The last letter from the bank simply stated he owed ...

You are a new financial analyst for acme bank and funeral

You are a new financial analyst for Acme Bank and Funeral Directors (they decided to diversify). Anyway you are looking at the following for a company you are considering for a loan. Sales = $650,000, their operating pro ...

Magenta corporation wants to raise 508 million in a

Magenta corporation wants to raise 50.8 million in a seasoned equity offering, net of all fees. Magenta stock currently sells for $14 per share. The underwriters will require a spread of $.50 per share, and indicate that ...

What is the cost of debt financing for a perpetual bond

What is the cost of debt financing for a perpetual bond selling for $948 if the semiannual coupon is $35, if the investment bank charges $5.40 per bond? (assume the firm is in a 40% tax bracket)

Corporate finance questionan investment pays you 30000 at

Corporate Finance Question: An investment pays you $30,000 at the end of this year, and $10,000 at the end of each of the four following years. What is the present value (PV) of this investment, given that the interest r ...

The satellite shoppe has current sales per share of 840 the

The Satellite Shoppe has current sales per share of $8.40. The sales per share are expected to increase at an annual rate of 12%. The historical P/E ratio is 16.2 and the historical P/S ratio is 7.6. What is the expected ...

What is the present value of a 3-year annuity of 170 if the

What is the present value of a 3-year annuity of $170 if the discount rate is 5%?  (Do not round intermediate calculations. Round your answer to 2 decimal places.)

A firm has 21000000 of available retained earnings the

A firm has $21,000,000 of available retained earnings. The capital structure is 48% debt, 8% preferred equity and 44% common equity. At what point in total funding will the company exhaust its available retained earnings ...

You are considering an investment in a 40-year security the

You are considering an investment in a 40-year security. The security will pay $25 a year at the end of each of the first three years. The security will then pay $30 a year at the end of each of the next 20 years. The no ...

Question - you are given one-year stock options with an

Question - You are given one-year stock options with an exercise price of $30. The current stock price is $30, so the options are at-the-money. Without hedging, the stock price at year-end will either be $28 or $38 with ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As