Assume that Blackstand corporation has a contract to build a ship for $1000.And a reliable estimate for total cost is $800.Project cost incurred are as follows:
Project cost : 2013 - $400 2014-$300 2015 - $100
Determine the Net Income using the percentage of completion for the year 2014.