Q1) Create network for aerospace launch project below and determine its critical path.
Activity
|
TE (weeks)
|
Preceding Activities
|
a
|
3
|
none
|
b
|
5
|
a
|
c
|
3
|
a
|
d
|
1
|
c
|
e
|
3
|
b
|
f
|
4
|
b, d
|
g
|
2
|
c
|
h
|
3
|
g, f
|
i
|
1
|
e, h
|