Q1) In following table are listed tasks, duration in weeks and predecessors.
Task
|
Duration in weeks
|
Predecessors
|
a
|
-
|
2
|
b
|
-
|
2
|
c
|
a, b
|
4
|
d
|
c
|
3
|
e
|
a, b, c
|
1
|
f
|
d, e
|
2
|
g
|
f
|
3
|
h
|
g
|
1
|
a) Create Gantt chart using MSP.
b) Suppose the 5 day workweek, compute critical path of the project.
c) Compute the project duration.
Q1) Let the following table:
|
PRET. ACT
|
TIME ESTIMATES (days)
|
Activity
|
|
to
|
tml
|
tp
|
te
|
A
|
-
|
6
|
6
|
6
|
|
B
|
A
|
4
|
5
|
6
|
|
C
|
A
|
2
|
4
|
6
|
|
D
|
B
|
4
|
6
|
8
|
|
E
|
C
|
1
|
3
|
5
|
|
F
|
D
|
1
|
5
|
3
|
|
i) Determine the likelihood of this project being completed earlier than 19 days between 13 and 15 days?