Computation of present value of a liability
Miner Industries develops an open pit uranium mine and is required to restore the mine area to a natural state at the end of the mine's useful life of 18 years. It is estimated that the restoration will cost $2,360,000 at that time. What is the present value of this liability given an interest (discount) rate of 7%?