Case : Cost Estimation at Global Green Books Publishing

Global Green Books Publishing is continuing to produce customised eBooks as a key new product line for it as a successful printing and publishing company. It has developed a template to help plan job orders. The major customer for these customised eBooks is a local college, who expected these books to be delivered at a low cost, and the company has not always been doing that. The Accounting department in Global Green Books was having difficult tracking the costs for each of the books.

Each eBook had a separate job order prepared that listed all the steps that needed to be completed, so that tasks could be assigned to each worker and costs estimated. With the existing job orders, estimates of time required for each task were sometimes not completed until after the work was done, causing problems as workers were supposed to move on to new tasks but were still finishing their previous tasks. Some tasks required specialised equipment or skills, sometimes from other groups within Global Green Books.

Along with its template for job orders, Global Green Books wanted to start developing a project estimate for each new eBook project. This cost estimate should capture direct costs and indirect costs. The direct costs for an eBook project include labour costs for those in the company working on the project, materials costs (if any), subcontractor or outside labour, and equipment and facility costs. Material costs for these eBooks include any permissions costs for content and images used in the eBook. Indirect costs for these eBooks computer support costs and sales commissions for each eBook project.

Phase

Task

Staff

Category

Rate ($)

Hours

Receive Order

Receive Order

Customer Service Representative

CSR

12.00

0.25 *

Receive Order

Check Order

Customer Service Representative

CSR

12.00

0.50 *

Receive Order

Verify Order

Customer Service Representative

CSR-1

16.00

1.0 *

Plan Order

Plan Work

Supervisor

Senior-1

28.00

1.0

Plan Order

Assign Work

Supervisor

Senior-1

28.00

1.0

Plan Order

Estimation

Supervisor

Senior-1

28.00

1.0

Plan Order

Reserve Equipment

Supervisor

Senior-1

28.00

.50

Production

Acquire Permissions

Publishers Liaison

PL

22.00

0

Production

Desktop Publishing (DTP)

DTP Specialist

DTP-2

18.00

12.5

Production

Content Conversion

DTP Specialist

DTP-1

12.50

4.0

Production

Produce eBook (Proof and Final)

DTP Specialist

DTP-2

18.00

5.0

Production

Quality Checks

Quality Technician Customer Service Representative

QC CSR-1

16.00

16.00

3.0

1.0

Manage Production

Track Production

Supervisor

Senior-1

28.00

3.0

During the Plan Order Phase, the hours for the Receive Order phase (marked with an *) are actual times, as this work has already been performed.

In addition to these internal labours costs, the Production Supervisor has estimated that the European History eBook will incur these costs:

- An overhead rate on all direct labour of 1.50.
- Material costs of $1,000 for each permission needed
- Equipment costs of $800 for unique equipment needed for this project (a special oversize map scanner)
- Subcontract labour of $500 for installation and training in the use of the oversize map scanner
- Computer support costs of $600
- Sales commission of 20%

In addition to direct and indirect costs, Global Green Books targets a 25% profit margin on each project, and budgets for a 10% contingency on labour and 20% contingency on permissions.

Comment on the following aspects of the case study:

a) What are the types of direct costs identified in this case? Why are they viewed as direct costs?

b) What are two forms of costs identified?

c) What are some problems that might arise that could impact the budget?

d) Why would Global Green Books set aside contingencies? How would needed rework, if caught in the quality reviews, be accounted for in the budget?

e) What are the main cost drivers of this project?

f) What other information, if any, would you like to see included in the budget for this project? Why?

Create a budget for the European History eBook project.

a) What are the costs by major phases of work for making this European History eBook?

b) What are the total costs for direct labour?

c) What is the total estimated cost of this European History eBook?

Risk Management, Finance

  • Category:- Risk Management
  • Reference No.:- M91820652
  • Price:- $35

Guranteed 24 Hours Delivery, In Price:- $35

Have any Question?


Related Questions in Risk Management

Respond to the following scenario with your thoughts ideas

Respond to the following scenario with your thoughts, ideas, and comments. Be substantive and clear, and use research to reinforce your ideas. Apix is considering coffee packaging as an additional diversification to its ...

Financial derivatives and risk management homework -1 this

Financial Derivatives and Risk Management Homework - 1. This is September, and you have $4,000 to invest for three months. The stock price is currently $40. A December call option with a $40 strike price is currently sel ...

Students will be randomly allocated to bushfire disaster

Students will be randomly allocated to Bushfire disaster scenarios and asked to complete a disaster response plan. The plan must cover all the relevant elements described in the unit and be an appropriate response for th ...

Advanced project risk management assignment -aim the aim of

Advanced Project Risk Management Assignment - Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project us ...

Problem 1ben traders a privately held us metals broker has

Problem 1: Ben Traders, a privately held U.S. metals broker, has acquired an option to purchase one million kilograms of partially refined molyzirconium ore from the Zeldavian government for $5.00 per kilogram. Molyzirco ...

Problem 1how much will an employees portfolio be worth

Problem 1: How much will an employee's portfolio be worth after working for the company 30 years more? The Human Resource department at EcoCarnifex Corporation was asked to develop a financial planning model that would h ...

Safety and risk management are critical aspects of a

Safety and Risk Management are critical aspects of a workplace and breaches are punishable under Work Health and Safety Law. This task encourages students to analyse and conceptualise responses to safety breaches in a gi ...

Problem 1 you are the mechanical engineer in charge of

Problem 1: You are the mechanical engineer in charge of maintaining the machines in a factory. The plant manager has asked you to evaluate a proposal to replace the current machines with new ones. The old and new machine ...

Financial risk management assignment - part a - part a

FINANCIAL RISK MANAGEMENT ASSIGNMENT - Part A - Part A requires you to complete the modules of "Economic Indicators" and "Fixed Income" of Bloomberg Market Concepts (BMC), which takes about 4 hours (1 hour for "Economic ...

Question - for a western business of your choice please let

Question - For a western business of your choice, (please let me know what you chose) Briefly describe the business, scan the environment, and list one risk you've identified to implement an ERM. Describe the risks and e ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As