Ask Business Law & Ethics Expert

Background

The Innsmouth Central School District (the "District") in upstate New York planned to build a new athletic field, with stadium seating and other facilities (locker rooms, showers, etc.), on its property located along the Northern bank of the Miskatonic River (the "Project"). After competitive bidding, the District properly awarded the site work contract (the "Contract") to Lovecraft, Inc. ("Lovecraft") for a lump sum of $450,000.

Relevant Contract Terms

The Contract required Lovecraft to clear and excavate the site, including an area close to the Miskatonic River bank, where a rare, wild plant known as Yog-Sothoth was growing, and to level and restore the excavated area by refilling it with Yog-Sothoth-free soil and grass. Other notable provisions in the Contract are as follows:

PERMITS. Owner shall obtain all necessary permits for Contractor's Work on the Project.

CHANGE IN CONTRACT PRICE OR TIME. If Contractor wishes to make a claim for an increase in the Contract Price or an extension of time to perform the Work, Contractor shall give Owner written notice within 24 hours after the event giving rise to such claim. Such written notice shall specify the condition or circumstance on account of which such claim is asserted, and shall specify the increase in the Contract Price and/or time to perform which Contractor believes is justified on account of such condition or circumstance. Failure to strictly comply with the requirements of this paragraph shall result in a waiver of Contractor's claim.

NO DAMAGE FOR DELAY. Contractor agrees not to make any claim for delay costs, loss of productivity or efficiency, lost profits or extended home office overhead, on account of any delay, obstruction or hindrance for any cause whatsoever, whether or not foreseeable, whether or not anticipated and whether or not caused by Contractor.

Under Education Law § 3813 (a statute relating to claims against a school district), a contractor must present a written, verified notice of claim to a school district within 3 months of the date the school district rejects or denies the contractor's claim for payment under a contract. See New York Construction Law Manual, 2013 ed., § 7:18. Once the contractor has submitted its verified notice of claim, the contractor has 1 year to sue the school district to recover on the claim, running from the date of the denial or rejection of the claim.

The Dispute

Lovecraft began work on the Project on April 1, 2012. On July 1, 2012, the New York State Department of Environmental Conservation (the "DEC") ordered all work on the Project stopped because the District had failed to obtain a permit required under a Federal law that protected Yog-Sothoth. As a result, Lovecraft was prevented from working until the necessary permit was obtained. Lovecraft's equipment and personnel remained on site during the stoppage period.

On November 1, 2012, the District advised Lovecraft that it had obtained the required permit and ordered Lovecraft to recommence work. Lovecraft started working again, but by November 15, 2012, the ground was frozen and Lovecraft was unable to excavate or otherwise continue working on the Project.

On November 15, 2012, Lovecraft sent a letter to the District indicating that Lovecraft was entitled to a reasonable extension of time and compensation for the delay occasioned by the DEC's stop work order and the schedule's slippage into the winter. On December 13, 2012, the District wrote back to Lovecraft, rejecting Lovecraft's claim for an extension of time and compensation for the delay. Lovecraft kept its equipment on site, but was unable to resume work until March 15, 2013.

On April 1, 2013, the DEC issued yet another stop work order for the Project because the District had not actually obtained the necessary permit. The permit finally came on May 30, 2013. Lovecraft was back to work on June 1, 2013 and completed work on September 1, 2013.

On September 2, 2013, Lovecraft sent its final payment application to the District, which included costs due to delays (i.e., the costs to keep its equipment and personnel on site during the stoppage periods and the winter months when work was unfeasible). On September 30, 2013, the District sent notice to Lovecraft that its final payment application was rejected because "the delay costs are barred under the Contract." On October 15, 2013, Lovecraft serves a written, verified notice of claim for its contract balance and delay damages on the District.

Assume that, on December 12, 2013, Lovecraft sues the District for breach of contract, seeking its contract balance and delay damages. How will the lawsuit play out?

Business Law & Ethics, Finance

  • Category:- Business Law & Ethics
  • Reference No.:- M91034215
  • Price:- $20

Priced at Now at $20, Verified Solution

Have any Question?


Related Questions in Business Law & Ethics

Assignment -purpose - this significant task requires

Assignment - Purpose - This significant task requires forward planning and adequate time for research, reading and reflecting. The purpose of the assignment is to enable you to achieve outcomes in knowledge, skill and ap ...

Group report1 this group assignment consists of 2 parts

GROUP REPORT 1. This group assignment consists of 2 parts. Part A is a case study on contract law, and Part B is a question involving Corporations Law. Both questions must be answered. 2. The total word limit for the gro ...

Managing the legal environment assignment - research

MANAGING THE LEGAL ENVIRONMENT ASSIGNMENT - RESEARCH PROJECT Company: Nike (a) Summarise in about 250-500 words the characteristics/features of the organisation (you can choose a statutory/government body or select a bus ...

Corporations law - assignment questions -objectives -

CORPORATIONS LAW - ASSIGNMENT QUESTIONS - Objectives - Answer the following questions with reference to the relevant statute law and general common law principles operating in Australia concerning the consequences of the ...

Business law assignment question -mabo has been said to a

BUSINESS LAW ASSIGNMENT QUESTION - Mabo has been said to a cornerstone of the Australian legal system. Your response must discuss the following: 1. Discussion of the Mabo (No 2) case. 2. Explain the impacts of the case o ...

Assignment - advanced financial accounting1 classification

Assignment - Advanced Financial Accounting 1. 'Classification of liabilities is based on the same principles as the classification of assets.' Do you agree with this? Why or why not? 2. 'Classification of liabilities as ...

Property law for business assignment question -mrs betty

PROPERTY LAW FOR BUSINESS ASSIGNMENT QUESTION - Mrs Betty Joyce lives in an old, war-time vintage army shed in Baldivis. When she started to live in the shed, in the early 1960s, the whole area was a remote backwater. Si ...

Compare and contrast tort law and criminal law explain the

Compare and contrast tort law and criminal law. Explain the purpose of the law of torts in contract to the purposes of criminal law. Why are they different? Support your answer using specific examples from the textbook.

Assessment taskassignment questiondiscussi the main ways

Assessment Task Assignment question: Discuss: i. the main ways that a company may source finance; and ii. the benefits and costs associated with the main sources of corporate finance. Guidance - Students are to read text ...

Australian commercial and corporations law assignment -this

Australian Commercial and Corporations Law Assignment - This assignment deals with critical problem solving skills. This assessment tests course objectives addressing: Knowledge of relevant law, Application of the law to ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As