1) Following are elements of a WBS for a project to build a bunk bed. Using the information supplied here, create a WBS and carry out a bottom-up cost estimate.

2) Following is a listing of items to be considered in costing a PC game development project.  Use this data to develop a parametric estimate of the cost of the project.

3) For the table below

  1. Create a PERT/CPM chart
  2. Identify the critical path and compute project duration
  3. Compute Latest Start, Earliest Start, and Float (Slack)

PART 2:

1) The following table shows the allocation of work assignments and resources needed for an investment firm to make a decision on investing in company XYZ.

  1. Create Responsibility Matrix
  2. Create Resource Gantt Chart
  3. Create Resources Loading Chart

2) Building a swimming pool

  1. Create a Gantt chart from the work breakdown structure.
  2. Create a PERT/CPM network showing the interdependencies of the different activities.   How long will the project take?  (Note:  Don't forget to take "elapsed time" into account.)
  3. Using the information in your Gantt chart, as well as the information on wage rates and cost of materials, put together a budget showing planned total expenditures for the project.

3) Following are cost and schedule data for a project that is underway.

  1. Using the cost data in the cost table above, create a cumulative cost curve comparing actual versus planned costs
  2. Using the schedule data in the schedule table above, create a Gantt chart comparing actual versus planned schedule performance
  3. Summarize in words what you see project status to be at this time. What do you predict regarding the final cost and final schedule for the project?

PART 3: Following are data reporting progress on a project. Work on all tasks contained in the table is scheduled to be complete as of the day of the report.

 

Budget

Begun?

Complete?

Actual cost

Earned Value

Task A

3,100

Yes

Yes

3,100

 

Task B

4,000

Yes

Yes

4,500

 

Task C

2,500

Yes

Yes

2,250

 

Task D

4,000

Yes

No

3,500

 

Task E

3,500

Yes

Yes

4,000

 

Task F

2,500

No

No

0

 

  1. Using the 50-50 Rule, what is earned value for this project?
  2. Using the 0-100 Rule, what is earned value for this project?
  3. Note the discrepancy of earned value figures when using the 50-50 Rule and 0-100 Rule. Why is there a discrepancy? Which Rule should we use? Explain your rationale.
  4. Using the 50-50 Rule earned value computation, what is schedule variance for the project as reported?
  5. What is the schedule performance index (SPI)?
  6. Using the 50-50 Rule earned value computation, what is the cost variance for the project as reported?
  7. What is the cost performance index (CPI)?
  8. If the total budget for this project is 50,000, use CPI to compute estimate at complete (EAC).

9) Using the earned value information garnered from the above table, provide your boss a brief status report on project progress to date. Also,provide projections for future status.

Financial Management, Finance

  • Category:- Financial Management
  • Reference No.:- M92853261

Have any Question?


Related Questions in Financial Management

Assignment problems1 on the day harry was born his parents

Assignment Problems 1. On the day Harry was born, his parents put $1600 into an investment account that promises to pay a fixed interest rate of 5 percent per year. How much money will Harry have in this account when he ...

1 activities of a company that require the spending of cash

1) Activities of a company that require the spending of cash are known as: A) Uses of cash. B) Cash on hand. C) Cash receipts. D) Sources of cash. E) Cash collections. 2) Relationships determined from a firm's financial ...

Module discussion forumto prepare for this discussion

Module : Discussion Forum To prepare for this discussion, review "Basics of Speechwriting" and "Basics of Giving a Speech" in textbook Chapter 15. Then watch this video of Apple founder and CEO Steve Jobs giving the 2005 ...

Launching a new product linefor this portfolio project

Launching a New Product Line For this Portfolio Project Option, you will act as an employee in a large company that develops and distributes men's and women's personal care products. The company has developed a new produ ...

Question 1 discuss valuing bonds and how interest rates

Question : 1) Discuss valuing bonds and how interest rates affect their value. Also consider the importance of the yield-to-maturity (YTM). 2) Discuss common stocks and preferred stocks. Also, which common stock valuatio ...

Introductionlast week you determined the root causes of the

Introduction Last week, you determined the root cause(s) of the problem you are trying to resolve for your final paper. As a reminder, the decision you are working on is the one that you selected in week two. This week, ...

You have owned and operated a successful brick-and-mortar

You have owned and operated a successful brick-and-mortar business for several years. Due to increased competition from other retailers, you have decided to expand your operations to sell your products via the Internet. ...

You will be conducting an interview with a market research

You will be conducting an interview with a market research professional or a company representative. Use the results of your research to make specific recommendations on how market research can be applied to the Marketpl ...

Question 1 what is marketing research what are the two

Question 1: What is marketing research? What are the two primary types of research? Question 2: What factors influence marketing research? Question 3: The role of statistics in business decision-making? Assignment : Sele ...

Chapter 74 for commercial banks what is meant by a managed

Chapter 7 4. For commercial banks, what is meant by a managed liability? What role do liquid assets play on the balance sheet of commercial banks? What role do money market instruments play in the asset and liability man ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As