Ask Statistics and Probability Expert

Analytical Models in DSS

A company that assembles electronic alarm systems requires three component parts: C1, C2, and C3. In-house production costs are estimated to be $15 per unit for part C1, $18 per unit for part C2, and $ 20 per unit for part C3.  It requires 0.16 hours of machining time and 0.1 hours of finishing time to produce to each unit of part C1 in-house; 0.3 hours of machining time and 0.2 hours of finishing time to produce to each unit of part C2 in-house; and 0.25 hours of machining time and 0.3 hours of finishing time to produce to each unit of part C3 in-house.

Because of contractual obligations the company needs 6,000 units each of parts C1, C2, and C3 in the upcoming week. It has only 3000 hours of machining time and 2400 hours of finishing time available over this period. Since its limited production capacity prevents it from satisfying its entire demand for these parts through in-house production alone, the company also needs to purchase some quantities of these parts from external suppliers.

Two external suppliers are available - Supplier A and Supplier B. Supplier A can supply at most 1000 units of C1 at a cost of $16 per unit, at most 1500 units of C2 at a cost of $20 per unit, and at most 1000 units of C3 at a cost of $24 per unit. Supplier B can supply at most 1200 units of C1 at a cost of $18 per unit, at most 2000 units of C2 at a cost of $22 per unit, and at most 1000 units of C3 at a cost of $23 per unit.

For your convenience, the information presented above is summarized in the table below.

Part

Cost per unit

Quantity

Capacity (units)

Hours required per unit

In-house

Supplier A

Supplier B

Required

Supplier A

Supplier B

Machining

Finishing

C1

 $  15

 $ 16

 $   18

6000

1000

1200

0.16

0.10

C2

 $  18

 $  20

 $    22

6000

1500

2000

0.30

0.20

C3

 $  20

 $  24

 $    23

6000

1000

1000

0.25

0.30

 







Available (hours)

 







Machining

Finishing

 

 

 

 

 

 

 

3000

2400

The company uses a decision support system to determine the optimal production and purchase plan for parts C1, C2, and C3 so as to meet their needs (contractual obligations in the upcoming week) at minimum cost.  It also uses the decision support system to perform sensitivity analysis.

a) What is the minimum cost attainable under the optimal plan?

The company has located a third supplier (New-Supplier) who can supply at most 100 units of part C1 in the upcoming week, but the purchase price is subject to negotiations. What is the maximum price that the company should be willing to pay New-Supplier for each unit of C1? Justify your answer. Assume that all demands, prices, and availability of resources remain unchanged.

Statistics and Probability, Statistics

  • Category:- Statistics and Probability
  • Reference No.:- M91639946
  • Price:- $30

Priced at Now at $30, Verified Solution

Have any Question?


Related Questions in Statistics and Probability

Introduction to epidemiology assignment -assignment should

Introduction to Epidemiology Assignment - Assignment should be typed, with adequate space left between questions. Read the following paper, and answer the questions below: Sundquist K., Qvist J. Johansson SE., Sundquist ...

Question 1 many high school students take the ap tests in

Question 1. Many high school students take the AP tests in different subject areas. In 2007, of the 144,796 students who took the biology exam 84,199 of them were female. In that same year,of the 211,693 students who too ...

Basic statisticsactivity 1define the following terms1

BASIC STATISTICS Activity 1 Define the following terms: 1. Statistics 2. Descriptive Statistics 3. Inferential Statistics 4. Population 5. Sample 6. Quantitative Data 7. Discrete Variable 8. Continuous Variable 9. Qualit ...

Question 1below you are given the examination scores of 20

Question 1 Below you are given the examination scores of 20 students (data set also provided in accompanying MS Excel file). 52 99 92 86 84 63 72 76 95 88 92 58 65 79 80 90 75 74 56 99 a. Construct a frequency distributi ...

Question 1 assume you have noted the following prices for

Question: 1. Assume you have noted the following prices for paperback books and the number of pages that each book contains. Develop a least-squares estimated regression line. i. Compute the coefficient of determination ...

Question 1 a sample of 81 account balances of a credit

Question 1: A sample of 81 account balances of a credit company showed an average balance of $1,200 with a standard deviation of $126. 1. Formulate the hypotheses that can be used to determine whether the mean of all acc ...

5 of females smoke cigarettes what is the probability that

5% of females smoke cigarettes. What is the probability that the proportion of smokers in a sample of 865 females would be greater than 3%

Armstrong faber produces a standard number-two pencil

Armstrong Faber produces a standard number-two pencil called Ultra-Lite. The demand for Ultra-Lite has been fairly stable over the past ten years. On average, Armstrong Faber has sold 457,000 pencils each year. Furthermo ...

Sppose a and b are collectively exhaustive in addition pa

Suppose A and B are collectively exhaustive. In addition, P(A) = 0.2 and P(B) = 0.8. Suppose C and D are both mutually exclusive and collectively exhaustive. Further, P(C|A) = 0.7 and P(D|B) = 0.5. What are P(C) and P(D) ...

The time to complete 1 construction project for company a

The time to complete 1 construction project for company A is exponentially distributed with a mean of 1 year. Therefore: (a) What is the probability that a project will be finished in one and half years? (b) What is the ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As