A project was planned using PERT with three times estimates. The expected completion time of the project was determined to br 40 weeks. The variance of the critical path is 9.

A What is the probability that the project will be finished in 40 weeks or less?

B. What is the probability that the project takes longer than 40 weeks?

C. What is the probability that the project will finished in 46 weeks?

D. What is the probability that the project tilll take longer than 46 weeks?

E. The project manager wishes to set the due date for the completion of the project so that there is a 90% chance of finishing on schedule. Thus, there would only be a 10% chance the project would take longer than this due date. What should this due date be?

Statistics and Probability, Statistics

  • Category:- Statistics and Probability
  • Reference No.:- M91007084

Have any Question?


Related Questions in Statistics and Probability

Let x be the random variable that represents the life in

Let X be the random variable that represents the life in hours of a certain electronic device. The probability density function of X X is f(x)=360x 3 f(x)=360x3 , 10≤x≤15 10≤x≤15. Find the expected life of this device.

A puck company wants to sponsor the players with the 20

A puck company wants to sponsor the players with the 20% quickest goals in hockey games. The times of first goals are normally distributed with a mean of 8.54 minutes and a standard deviation of 4.91 minutes. How fast wo ...

If you know your raw score is 35 your z score is -3 and

If you know your raw score is 35, your z score is -3, and your t score is 20. The mean is 50 and the standard deviation is 5. How would you use this information to solve for a percentile rank?

A factory manager must decide whether to stock a particular

A factory manager must decide whether to stock a particular spare part. The part is absolutely essential to the operation of certain machines in the plant. Stocking the part costs $10 per day in storage and cost of capit ...

A group of students made the following scores on a 10-item

A group of students made the following scores on a 10-item quiz in psychological statistics: {5, 6, 7, 7, 7, 8, 8, 9, 9, 10, 10} What is the variance, treating these scores as a sample?

A 2-year treasury security currently earns 197 percent over

A 2-year Treasury security currently earns 1.97 percent. Over the next two years, the real risk-free rate is expected to be 1.00 percent per year and the inflation premium is expected to be 0.60 percent per year. Calcula ...

Basic statisticsactivity 1define the following terms1

BASIC STATISTICS Activity 1 Define the following terms: 1. Statistics 2. Descriptive Statistics 3. Inferential Statistics 4. Population 5. Sample 6. Quantitative Data 7. Discrete Variable 8. Continuous Variable 9. Qualit ...

What is the appropriate statistical analysis to use t-test

What is the appropriate statistical analysis to use: t-test for two independent samples, t-test for dependent samples, ANOVA, or chi-square test of independence? Please identify and explain why it is appropriate. (a) A s ...

Analysis of variance anovaan investigator compares the

Analysis of variance (ANOVA) An investigator compares the difference in the amount of 20% sucrose solution removed by pollinators between unadulterated solution and solutions with 50, 100, 150, and 200 parts per million ...

1 three-circle red-on-white is one distinctive pattern

1) Three-circle, red-on-white is one distinctive pattern painted on ceramic vessels of the Anasazi period found at an archaeological site. At one excavation, a sample of 165 potsherds indicated that 74 were of the three- ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As