A Project has just completed the 87th item in its action plan. It was scheduled to have spent $168,000 at this point in the plan but has actually spent only $156,000. The foreman estimates that the value of the work actually finished is about $162, 000. What are the spending and schedule variances for the project? What are the SPI and CPI?

Basic Finance, Finance

  • Category:- Basic Finance
  • Reference No.:- M91072120

Have any Question?


Related Questions in Basic Finance

Industries recently commissioned management consultants to

Industries recently commissioned management consultants to estimate an appropriate rate for investment projects with the same risk as the firm. Unfortunately, part of the report was lost, and you have been asked to calcu ...

What are the top 5 dos and donts regarding e-portfolio each

What are the top 5 "do's and don't's regarding e-portfolio? each one of your 5 do's and don't's from your perspective and how it affected your authoring your e-portfolio content and construction. i need some help I;m doi ...

Suppose you want to raise 15m for a new machine you plan to

Suppose you want to raise $15m for a new machine. You plan to raise the funds by selling 20-year $1,000 bonds with a semi-annual coupon rate of 5% and 8% yield. Before putting the bonds to market, inflation drops half a ...

Georgia a widow has take-home pay of 2000 a week her

Georgia, a widow, has take-home pay of $2,000 a week. Her disability insurance coverage replaces 70 percent of her earnings after a four-week waiting period. What amount would she receive in disability benefits if an ill ...

With its current leverage cowcow copr will have net income

With its current leverage, COWCOW copr will have net income next year of $7 million. If COWCOWs corporate tax rate is 30% and it pays 7% interest on its debt, how much debt can COWCOW issue this year and still receive th ...

1nbsphow do the geometric and arithmetic average dividend

1. How do the geometric and arithmetic average dividend growth rates compare when the annual growth rates are positive? A. The arithmetic average dividend growth rate is generally larger than the geometric average growth ...

Suppose you want to raise 15m for a new machine you plan to

Suppose you want to raise $15m for a new machine. You plan to raise the funds by selling 20-year $1,000 bonds with a semi-annual coupon rate of 5% and 8% yield. Before putting the bonds to market, inflation drops half a ...

Stock x has a beta coefficient of 20 and stock y has a beta

Stock X has a beta coefficient of 2.0 and stock Y has a beta coefficient of 1.5. The expected rate of return on an average stock is 11% and the risk-free rate is 5%. By how much does the required rate of return on the ri ...

What is marketing discipline what is most peoples

What is marketing discipline? What is most people's perception of marketing discipline? Name an organization that has done a great job marketing. What did they do to make you feel this way?

Question - a soil weighs 1282 kgm3 loose 1602 kgm3 in place

Question - A soil weighs 1282 kg/m3 loose, 1602 kg/m3 in place and 1842 kg/m3 compacted. Find the swell and shrinkage of this soil and if a scraper has a heaped volume capacity of 33.6 m3, calculate how many Bm3 of soil ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As