A large school system is planning a renovation of a number of schools, all built prior to 1940. While making estimates for the budget, it was necessary to forecast the likely cost of renovation based on accumulated experience in past similar jobs. The cost data on old jobs has been updated to current conditions using the Engineering News-Record index. Data are as follows:

2008_current conditions using the Engineering.png

(a) Assume that the expected cost of renovation is linear with the number of rooms. Estimate the regression line and show the relationship on a plot with the data. Estimate σ and plot lines 1 standard deviation each side of the mean value function. Estimate and plot 1-standard-deviation confidence limits on the mean value.

(b) If the first job to be studied contains 32 rooms, use the results of (a) to make statements about its

expected cost and the standard deviation of this figure. Note that a single forecast of the random variable, i.e., cost, is desired.

(c) Data on the number of stories are given. Repeat the analysis using number of stories to predict the cost. The job contains three stories. Which independent variable-number of rooms or number of stories- gives a "more reliable" prediction of cost?

Statistics and Probability, Statistics

  • Category:- Statistics and Probability
  • Reference No.:- M92681313

Have any Question?


Related Questions in Statistics and Probability

Please show all worka pair of dice is tossed and the face

Please show all work. A pair of dice is tossed and the face number of each die is recorded. Assuming the dice are fair, what's the probability of the sum of the die faces showing is even?

For a population of individuals that has a standard

For a population of individuals that has a standard deviation of 10, what is the standard error of the mean for samples of size (a) 2, (b) 3, (c) 4, (d) 5, (e) 10, (f) 20, (g) 100?

A bottle of water is supposed to have 12 ounces the

A bottle of water is supposed to have 12 ounces. The bottling company has determined that 98% of bottles have the correct amount. Which of the following describes a binomial experiment that would determine the probabilit ...

How does a market-maker decide the edge offset required to

How does a market-maker decide the edge (offset) required to perform an options trade? Explain why this edge would be different for options of different strikes as well as for option combinations?

On valentines day thenbspquiet nooknbsprestaurant offers

On Valentine's Day the  Quiet Nook  restaurant offers a  Lucky Lovers Special  that could save couples money on their romantic dinners. When the waiter brings the check he also brings a scratch-off ticket that the couple ...

A hypothetical population consists of eight individuals

A hypothetical population consists of eight individuals ages 13, 15, 17, 21, 22, 23, 26, and 30 years. (Enter your answers to three decimal places.) (a) What is the probability that a person in this population is a teena ...

When circuit boards used in the manufacture of compact disc

When circuit boards used in the manufacture of compact disc players are tested, the long  run percentage of defectives is 5%. Let X= the number of defective boards in random sample of size n=25, so X ~ Bin( 25, .05). a)  ...

The random variable x takes on the values 5 20 30 and 200

The random variable X takes on the values 5, 20, 30, and 200 with probabilites 0.60, 0.30, 0.08, and 0.02 respectively. Use the statistical capacity of your calculator to find the expected value of Xrounded to one place ...

Your client is going to be traveling to las vegas in the

Your client is going to be traveling to Las Vegas in the near future and he wants to place some bets on his favorite professional baseball team. To ensure he knows the odds on his bets he wants to know the probability of ...

The number of people arriving for treatment at an emergency

The number of people arriving for treatment at an emergency room can be modeled by a Poisson process with a mean of 7 people per hour. How many people do you expect to arrive during a 55-minute period?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As