Ask Statistics and Probability Expert

1. Arcs in a project network indicate

a. completion times.
b. precedence relationships.
c. activities.
d. None of the alternatives above is correct.

2. Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 12, 15, and 10, then the earliest start time for W

a. is 10.
b. is 12.
c. is 15.
d. cannot be determined.

3. When activity times are uncertain,

a. assume they are normally distributed.
b. calculate the expected time, using (a + 4m + b)/6.
c. use the most likely time.
d. calculate the expected time, using (a + m + b)/3.

4. Slack equals

a. LF - EF.
b. EF - LF.
c. EF - LS.
d. LF - ES.

5. Activities with zero slack

a. can be delayed.
b. must be completed first.
c. lie on a critical path.
d. have no predecessors.

6. Inventory

a. is held against uncertain usage so that a supply of items is available if needed.
b. constitutes a small part of the cost of doing business.
c. is not something that can be managed effectively.
d. All of the alternatives are correct.

7. Inventory models in which the rate of demand is constant are called

a. fixed models.
b. deterministic models.
c. JIT models.
d. requirements models.

8. Safety stock

a. can be determined by the EOQ formula.
b. depends on the inventory position.
c. depends on the variability of demand during lead time.
d. is not needed if Q* is the actual order quantity.

9. Inventory position is defined as

a. the amount of inventory on hand in excess of expected demand.
b. the amount of inventory on hand.
c. the amount of inventory on hand plus the amount of inventory on order.
d. None of the alternatives is correct.

10. For the EOQ model, which of the following relationships is incorrect?

a. As the order quantity increases, the number of orders placed annually decreases.
b. As the order quantity increases, annual holding cost increases.
c. As the order quantity increases, annual ordering cost increases.
d. As the order quantity increases, average inventory increases.

11. In the latter part of the class, we discussed at some length the case study entitled, "What's Happening?" Ultimately, the solution to the problem the owners are experiencing MUST involve...

a. a different forecasting method. The one they are using now does NOT have the minimal values of MAE or MSE.
b. more careful monitoring of inventory levels as well as usage of safety stock so as to avoid stock outs from recurring.
c. further study of their customer base so as to better understand the reasons for the declining demand.
d. use of a stochastic inventory management model such as the EOQ.

12. Decision makers in queuing situations attempt to balance

a. operating characteristics against the arrival rate.
b. service levels against service cost.
c. the number of units in the system against the time in the system.
d. the service rate against the arrival rate.

13. If arrivals occur according to the Poisson distribution every 20 minutes, then which is NOT true?

a. l = 20 arrivals per hour
b. l = 3 arrivals per hour
c. l = 1/20 arrivals per minute
d. l = 72 arrivals per day

14. In a waiting line situation, arrivals occur, on average, every 10 minutes, and 10 units can be received every hour. What are l and m?

a. l = 10, m = 10
b. l = 6, m = 6
c. l = 6, m = 10
d. l = 10, m = 6

15. The total cost for a waiting line does NOT specifically depend on

a. the cost of waiting.
b. the cost of service.
c. the number of units in the system.
d. the cost of a lost customer.

16. For many waiting line situations, the arrivals occur randomly and independently of other arrivals and it has been found that a good description of the arrival pattern is provided by

a. a normal probability distribution.
b. an exponential probability distribution.
c. a uniform probability distribution.
d. a Poisson probability distribution.

17. All of the following are true about time series methods except

a. They discover a pattern in historical data and project it into the future.
b. They involve the use of expert judgment to develop forecasts.
c. They assume that the pattern of the past will continue into the future.
d. Their forecasts are based solely on past values of the variable or past forecast errors.

18. Forecast errors

a. are the difference in successive values of a time series
b. are the differences between actual and forecast values
c. should all be nonnegative
d. should be summed to judge the goodness of a forecasting model

19. MAE and MSE for a given set of data will be

a. about the same for all data since they are both positive
b. different since one is square of the other
c. different in general, though both will be positive
d. different in general, though both will be negative

20. To select a value for alpha when using exponential smoothing

a. use a small alpha when the series varies substantially.
b. use a large alpha when the series has little random variability.
c. use a value between 0 and 1
d. All of the alternatives are true.

21. A company produces the financial results shown in the table below. The executives at the firm have good reason to believe that $10 million in sales will be generated in 2010. Using simple linear regression, you advise them that this will equate to...

Year Sales Totals (in millions) Profit Totals (in millions)
1998 $7.0 $0.15
1999 $2.0 $0.10
2000 $6.0 $0.13
2001 $4.0 $0.15
2002 $14.0 $0.25
2003 $15.0 $0.27
2004 $16.0 $0.24
2005 $12.0 $0.20
2006 $14.0 $0.27
2007 $20.0 $0.44
2008 $15.0 $0.34
2009 $7.0 $0.17

a. $209,600 in profits.
b. $2,096,000 in profits.
c. $186,900 in profits.
d. $1,869,000 in profits.


22. When the CEO asks you how sure you are of the accuracy of the result provided in Problem #21 above, you show her the r-squared value and respond...

a. "54% sure."
b. "67% sure."
c. "84% sure."
d. "93% sure."

23. Given the following linear programming problem with two non-negative variables

(X1 and X2 ), find the range of feasibility for the RHS of the second constraint shown below (hint: both constraints are binding)
Max:
Constraints:

Variables are non-negative

a. [52,780]
b. [62.4,90]
c. [52,62.4]
d. [62.4,780]

24. In a transportation problem with 5 supply points, 3 demand points, and total supply equaling total demand, the number of decision variables will be

a. 5
b. 8
c. 15
d. 125

25. In the linear programming formulation of the transportation problem, cost of transporting one unit of the material from a supply point to a demand point appears in

a. the objective function only
b. the constraints only
c. both objective function and constraints
d. neither objective function nor constraints

Statistics and Probability, Statistics

  • Category:- Statistics and Probability
  • Reference No.:- M91598005
  • Price:- $25

Priced at Now at $25, Verified Solution

Have any Question?


Related Questions in Statistics and Probability

Introduction to epidemiology assignment -assignment should

Introduction to Epidemiology Assignment - Assignment should be typed, with adequate space left between questions. Read the following paper, and answer the questions below: Sundquist K., Qvist J. Johansson SE., Sundquist ...

Question 1 many high school students take the ap tests in

Question 1. Many high school students take the AP tests in different subject areas. In 2007, of the 144,796 students who took the biology exam 84,199 of them were female. In that same year,of the 211,693 students who too ...

Basic statisticsactivity 1define the following terms1

BASIC STATISTICS Activity 1 Define the following terms: 1. Statistics 2. Descriptive Statistics 3. Inferential Statistics 4. Population 5. Sample 6. Quantitative Data 7. Discrete Variable 8. Continuous Variable 9. Qualit ...

Question 1below you are given the examination scores of 20

Question 1 Below you are given the examination scores of 20 students (data set also provided in accompanying MS Excel file). 52 99 92 86 84 63 72 76 95 88 92 58 65 79 80 90 75 74 56 99 a. Construct a frequency distributi ...

Question 1 assume you have noted the following prices for

Question: 1. Assume you have noted the following prices for paperback books and the number of pages that each book contains. Develop a least-squares estimated regression line. i. Compute the coefficient of determination ...

Question 1 a sample of 81 account balances of a credit

Question 1: A sample of 81 account balances of a credit company showed an average balance of $1,200 with a standard deviation of $126. 1. Formulate the hypotheses that can be used to determine whether the mean of all acc ...

5 of females smoke cigarettes what is the probability that

5% of females smoke cigarettes. What is the probability that the proportion of smokers in a sample of 865 females would be greater than 3%

Armstrong faber produces a standard number-two pencil

Armstrong Faber produces a standard number-two pencil called Ultra-Lite. The demand for Ultra-Lite has been fairly stable over the past ten years. On average, Armstrong Faber has sold 457,000 pencils each year. Furthermo ...

Sppose a and b are collectively exhaustive in addition pa

Suppose A and B are collectively exhaustive. In addition, P(A) = 0.2 and P(B) = 0.8. Suppose C and D are both mutually exclusive and collectively exhaustive. Further, P(C|A) = 0.7 and P(D|B) = 0.5. What are P(C) and P(D) ...

The time to complete 1 construction project for company a

The time to complete 1 construction project for company A is exponentially distributed with a mean of 1 year. Therefore: (a) What is the probability that a project will be finished in one and half years? (b) What is the ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As