Ask Question, Ask an Expert

+61-413 786 465

info@mywordsolution.com

Ask Managerial Accounting Expert

1. a. Find the schedule variance for a project that has an actual cost at month 22 of $540,000, a scheduled cost of $523,000, and an earned value of $535,000.

b. A project at month 5 had an actual cost of $34,000, a planned cost of $42,000, and value completed of $39,000. Find the schedule and cost variances.

c. A project at day 70 exhibits an actual cost of $78,000, a scheduled cost of $84,000, and a value completed of $81,000. Find the schedule and cost indices.

2. Consider the information about a project plan in the following table.

Task

Immediate

Predecessor

Duration

Scheduled

Cost/Day

A

-

3

$1,000

B

-

5

$2,000

C

A

4

$4,000

D

B

7

$1,000

E

C

6

$2,000

F

D

8

$3,000

The following table shows the weekly control reports for the first two weeks (assume 5 working days each week).

 

End of Week 1

End of Week 2

Task

Actual %

Completed

Cumulative

Actual Cost

Actual %

Completed

Cumulative

Actual Cost

A

60%

$1,500

100%

$ 2,900

B

30%

$3,000

100%

$11,000

C

10%

$2,000

100%

$13,500

D

0%

$        0

90%

$10,000

E

0%

$        0

50%

$ 4,000

F

0%

$        0

0%

$        0

a. Use the earned value approach to calculate BCWP, BCWS, ACWP, SV, CV, SI, and CI for each task and the whole project.

b. Calculate the total variance and time variance for the project at the end of week 2.

c. Use the original estimate approach and the revised estimate approach to respectively estimate the final cost of this project at the end of week 1.

d. Use the original estimate approach and the revised estimate approach to respectively estimate the final cost of this project at the end of week 2.

3. A manufacturer of communication systems currently overhauls its computerized payroll system. Instead of using LOC (lines of code) to track the effort on devel¬oping such a payroll system, the manufacturer adopts a more reliable method, function point analysis, for measuring/monitoring the progress of the project.

The new payroll system consists of eight modules, each with a certain amount of function points. From the manufacturer's experience, each function point takes one week to develop. The ongoing project is evaluated at the end of the eighth week after its start. The schedule/cost report is provided in the follow¬ing table. (Assume linearity of cost vs. function point in each module.)

Comment on the status of the project at the end of week 8 based on the calculation of the project BCWP, BCWS, and ACWP. Is the project "in control"?; if not, why not?

Module

Immediate
Predecessors

Function
Points

Budget
(K)

Completed
Function Point

Money Spent
(K)

A

 

4

$90

4

$110

B

A

3

$65

3

$ 35

C

A

6

$75

2

$ 40

D

B

3

$60

3

$ 75

E

C

8

$55

1

$ 20

F

C

2

$40

1

$ 10

G

D, E

5

$80

0

$ 0

H

F

7

$90

0

$ 0

4. Sandy Point is the project manager of a small project that consists of seven tasks. After careful and extensive planning, Sandy and her project staff agreed on a proposed project schedule that is indicated by the following Gantt chart:

As indicated in their original project plan, Sandy and her staff had estimated the following durations and (total) direct costs for each task:

Task

Duration (weeks)

Planned Value

A

4

$2800

B

7

$2800

C

3

$1150

D

5

$625

E

5

$1350

F

3

$1050

G

3

$270

This morning (beginning of week 6), Sandy received a progress report; as indicated in the Gantt chart, task C could not be started until this week due to the unexpected delay in completing task A. The report also indicates that task B has been completed two weeks earlier than expected. Information from the progress report is summarized in the following table.

Task Current Actual Percent of
Status Expenditures Work
  to Date Completed
A Completed $2,000 100%
B Completed $2,800 100%
C Just started $0 0%
D In progress $330 55%
E Not started $0 0%
F Not started $0 0%
G Not started $0 0%

a. As of today (beginning of week 6), what is the cost variance of the project? What is the schedule variance of the project?

b. Based on information provided to date, what is your assessment of the cur¬rent status of the project?

Managerial Accounting, Accounting

  • Category:- Managerial Accounting
  • Reference No.:- M91560392
  • Price:- $30

Guranteed 24 Hours Delivery, In Price:- $30

Have any Question?


Related Questions in Managerial Accounting

Assignment - essendon electronics regal or monarchessendon

Assignment - Essendon Electronics: Regal or Monarch? Essendon Electronics, a division of Elgin Ltd, manufactures a diverse range of electrical products. Its range includes two LCD screen television models: the Monarch, w ...

Accounting for decision makersproject - appendix

Accounting for Decision Makers PROJECT - APPENDIX A Requirements: 1. Choose a publicly traded company that you currently own/invest in or one that you would like to own / invest in 2. Research the company through the com ...

Task descriptionyou have gained a position as vacation

Task Description You have gained a position as vacation student at the accounting firm T&K Solutions. In your capacity of vacation student you have been asked by the two partners of T&K Solutions to assist them with two ...

Duncan arrowroot confectionery dacrequired in hard copy no

Duncan Arrowroot Confectionery (DAC) Required in hard copy no later than the class scheduled time on Thursday, October 18th. 1) Prepare a memo to the Controller explaining how you would go about classifying the various r ...

You need to prepare a paper about lacroix companycompany

You need to prepare a paper about Lacroix company Company: Lacroix Home Work: History & background Page: 1 and half

Corporate accounting assignment -assessment task - select

Corporate Accounting Assignment - Assessment task - Select two public limited companies listed on the Australian Securities Exchange (ASX) that are in the same industry. Go to the website of your selected companies. Then ...

Corporate accounting assignment -objectives -the

Corporate Accounting Assignment - Objectives - The educational objective of this task is to develop student capabilities to read, interpret and analyse financial statements; to apply international accounting standards; t ...

Instructions for preparation of assignment1 you are to

Instructions for Preparation of Assignment: 1. You are to choose one management accounting topic from the list below for this assignment, and register your chosen topic with your lecturer in class or via email before com ...

Managerial accounting assignment -background you are

Managerial Accounting Assignment - Background: You are recently employed as a graduate consultant in a management consultancy firm and are assigned to a team. One of your firm's clients is currently evaluating its budget ...

Managerial accounting assignment -instructions for

Managerial Accounting Assignment - Instructions for Preparation of Assignment: 1. You are to choose one management accounting topic from the list below for this assignment, and register your chosen topic with your lectur ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As