PROPOSAL A

Financial

Proposal A envisages generation of electricity from water - a hydro-electric project. The useful economic life of this project is estimated to be 60 years. This project will generate 50,000 million (mn) units of electricity annually. Electricity will be sold to the public at a tariff of 10 cents per unit. The annual operation and maintenance costs are expected to be 2.5 percent of the capital cost.

Economic (Social)

The economic (social) costs and benefits for this project must be estimated from Figure 1.

PROPOSAL B

Financial

Proposal B is a thermal project - electricity will be generated from coal. The annual operating costs for this project are estimated to be 5 percent of the capital cost. This project will also have a useful economic life of 60 years. It will generate 50,000mn units of electricity annually. The electricity from this project will be sold at 12 cents per unit.

Economic (Social)

The economic (social) costs and benefits for this project can be estimated from Figure 2.

Task

Your task is simply to summarize (in your own hand) the results of your analysis in the answer-sheet provided separately.

Notes:
- You must provide the background details (i.e., select calculations), for various answers provided by you in the answer-sheet, in an Annexure (no more than one double-sided page). You must type-write your Annexure. You must not attach any computer-generated spread-sheets in the Annexure. The minimum permissible font size for the Annexure is 12 (Times Roman or equivalent).

- The completed answer-sheet must however be a stand-alone document (i.e., the reader should be able to understand the entire logic behind your reasoning without needing to refer to the Annexure. You must however provide (in the annexure) background calculations for the reasoning provided by you for each question in the answer-sheet.

- There is no tolerance on specified word/page limits. Any written material beyond these limits will not be marked.

- Please tick only one box wherever a multiple choice is provided.

Assumptions (common to both proposals)

- All capital costs are incurred at time t=0 (i.e., ignore project construction time).

- Electricity generated, electricity tariffs, annual costs and the discount rate remain constant throughout the economic lives of the projects.

- The economic (social) costs and benefits must be estimated exclusively from Figures 1 and 2. The costs and benefits represented in these figures are all inclusive, i.e., total costs include capital and operating costs and the demand curves reflect of all benefits provided by the projects.

- For the purpose of estimation of economic (social) costs and benefits assume that the market structure for electricity sector is currently monopoly. It is expected to remain so for the first ten years of the project life-span. The government however proposes to transform this market initially into an oligopoly (for the years 11 to
30) and eventually competitive (years 31-60). While it is difficult to precisely estimate the price and quantity outcomes that will prevail in an oligopoly market, the economic brains of the time have suggested that these outcomes are as shown by dotted lines in Figures 1 and 2.

- The real and apparent annual discount rates are 10 and 15 percent, respectively. Further, the economic and financial discount rates can be assumed to be the same.

2173_Figure.jpg

Figure 1 Economic (Social) Costs and Prices: Proposal A

2233_Figure1.jpg

Figure 2 Economic (Social) Costs and Prices: Proposal B

Figures 1 and 2 are Not-to-scale. Therefore, do not use these figures to estimate various areas. You should instead use values on X and Y axes to estimate various areas.49003 ECONOMIC

Please summarize your results in the table below:

 

Financial

Economic

 

Proposal A

Proposal B

Proposal A

Proposal B

NPV

 

 

 

 

IRR

 

 

 

 

PB

 

 

 

 

B/C

 

 

 

 

Equivalent Annual Cost

 

 

 

 

Consumer Surplus

 

 

 

 

Producer Surplus

 

 

 

 

Total Surplus

 

 

 

 

Note: NPV; Equivalent Annual Cost; Consumer, Producer, and Total Surplus - must be rounded off to the nearest billion dollars (i.e., no decimals), and IRR and PB - to the nearest ‘whole' percent and years (i.e., no decimals), and B/C - to one decimal point, respectively.

1. Which proposal will you recommend from the consumer's perspective?

Why? Because

2. Which proposal will you recommend from the economy's perspective?

Why? Because

3. Will your recommendation, based on economic perspective, change if, due to technological malfunctioning, the useful life of proposal B gets reduced to 30 years?

4. Is there a co-relation between your estimates of Life Cycle Cost and Equivalent Annual Cost?

5. In Figure 2, the oligopoly price is 9 cents per unit. Will the response of demand to price decrease from 9 to 6 cents per unit be elastic or inelastic?

6. From economic perspective, what is the price elasticity of supply for Project B when the price of electricity increases from 6 cents per unit to 9 cents per unit (Figure 2). Assume market for electricity is competitive?

7. Prices are generally higher in oligopoly and monopoly markets as compared with those in competitive markets. This results in loss of welfare (deadweight loss). In order to improve welfare, the governments therefore either offer direct subsidies to the oligopoly and monopoly firms, or allow the firms to price-discriminate. Assume that the government has allowed the oligopoly and monopoly firms to price discriminate. For proposal A, what is the total value of subsidy (expressed in present value terms) that the government will need to offer to the oligopoly and monopoly firms, in order to encourage them to produce at competitive market levels of production?

Please present your calculations (or explanation)? (in no more than two steps)

8. Sensitivity analysis can be used to determine how the viability of a project is influenced by over- or under-estimation of various input variables. Assume that Total surplus is used as the criterion for assessing the viability of Project B. What is the ‘switching value' of ‘capital cost' for this project?

Please present your calculations? (in no more than two steps)

Microeconomics, Economics

  • Category:- Microeconomics
  • Reference No.:- M91996924

Have any Question?


Related Questions in Microeconomics

Question show the market for cigarettes in equilibrium

Question: Show the market for cigarettes in equilibrium, assuming that there are no laws banning smoking in public. Label the equilibrium private market price and quantity as Pm and Qm. Add whatever is needed to the mode ...

Question recycling is a relatively inexpensive solution to

Question: Recycling is a relatively inexpensive solution to much of the environmental contamination from plastics, glass, and other waste materials. Is it a sound policy to make it mandatory for everybody to recycle? The ...

Question consider two ways of protecting elephants from

Question: Consider two ways of protecting elephants from poachers in African countries. In one approach, the government sets up enormous national parks that have sufficient habitat for elephants to thrive and forbids all ...

Question suppose you want to put a dollar value on the

Question: Suppose you want to put a dollar value on the external costs of carbon emissions from a power plant. What information or data would you obtain to measure the external [not social] cost? The response must be typ ...

Question in the tradeoff between economic output and

Question: In the tradeoff between economic output and environmental protection, what do the combinations on the protection possibility curve represent? The response must be typed, single spaced, must be in times new roma ...

Question consider the case of global environmental problems

Question: Consider the case of global environmental problems that spill across international borders as a prisoner's dilemma of the sort studied in Monopolistic Competition and Oligopoly. Say that there are two countries ...

Question consider two approaches to reducing emissions of

Question: Consider two approaches to reducing emissions of CO2 into the environment from manufacturing industries in the United States. In the first approach, the U.S. government makes it a policy to use only predetermin ...

Question the state of colorado requires oil and gas

Question: The state of Colorado requires oil and gas companies who use fracking techniques to return the land to its original condition after the oil and gas extractions. Table 12.9 shows the total cost and total benefit ...

Question suppose a city releases 16 million gallons of raw

Question: Suppose a city releases 16 million gallons of raw sewage into a nearby lake. Table shows the total costs of cleaning up the sewage to different levels, together with the total benefits of doing so. (Benefits in ...

Question four firms called elm maple oak and cherry produce

Question: Four firms called Elm, Maple, Oak, and Cherry, produce wooden chairs. However, they also produce a great deal of garbage (a mixture of glue, varnish, sandpaper, and wood scraps). The first row of Table 12.6 sho ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As