Ask Question, Ask an Expert

+61-413 786 465

info@mywordsolution.com

Ask Cost Accounting Expert

HUB AEROSPACE

Review this case carefully and answer the questions at the end of the case in detail.

Hub Aerospace, Inc. was awarded a fixed-price-incentive contract for jet aircraft engines. The engines were assembled by Hub from components furnished by subcontractors. Hub had received competitive bids on all their components, which they had compiled, to come up with the bid price. Included in a number of these components was one termed a "chamber." Hub's make­ or-buy study in the pre-contract phase had concluded with the decision to buy 70 chambers from one of its subcontractors.

Mr. Brosky , the contracting officer, had reduced the target price by $58,751 pursuant to the clause on price reductions for defective cost or pricing data. His decision to take this action was based on information furnished him by the GAO, who found in their post-award audit under PL 87-653 that Hub had failed to disclose price quotations submitted by a subcontractor, Steele Tube and Pipe Company, in competition for the chambers. This subcontractor's quotation of 1 February 19XO to Hub had been a unit price of $16,211. Hub's proposal to the government was based on the unit price of $17,000 submitted by the Weller Steel Tube Company. The difference between these two vendor prices of $789, adjusted by contract pricing arrangement of 75/25, G&A and profit was the basis of Mr. Brosky 's price adjustment.

Also at issue is a substantial increase in the amount of price reduction based on another undisclosed quotation of $15,451, 3 June 19XO. This quotation was submitted by Steele after the prime contract negotiations were completed and after Hub had executed its certificate of current pricing but before signing the prime contract. Hub then awarded the subcontract to Steele at the reduced price.

The circumstances preceding award of the government's contract to Hub Aerospace, Inc. were substantially as follows:

The number of chambers to be purchased or to be made in-house under the make-or­ buy program was uncertain . Changes were made in the program and in the quantities to be quoted on by the subcontractors. In January 19XO, the range of prices per unit for chambers was as follows:

On 6 February 19XO, Weller's oral quotation for 144 units was given: $16,866 for delivery beginning in November. On 7 February l 9XO, Steele's written quotation for delivery in July 19XO was submitted as follows:

"The above prices are based on uninterrupted production at rates shown above commencing July 19XO."

The delivery conditions imposed by Steele made their quotations nonresponsive, since Hub's RFQ called for delivery in November, not July. Hub's · subcontracting Negotiation Memorandum showed an attempt to have Steele eliminate that condition, and their statement they would give some consideration to the effect on pricing if they complied with the delivery schedule. The Memorandum contained no evidence to show that when Hub submitted its proposal to the Governrnent in March 19XO, or before conclusions of the negotiations in May, that Steele had eliminated its delivery condition. On the basis of delivery, Hub accepted Weller's quotation of $16,866 adjusted to $17,000 because of program changes from 144 to 136.

The governrnent's Negotiation Memorandum reflected a close and cooperative relationship between Hub and the government personnel. The cost analyst could have learned of the quotation differences by asking for access to the chambers' procurement records. The government representatives were familiar with both Steele and Weller and when a make-or-buy decision arose they would be logical subcontracting sources. In relying on the cost and pricing data, the government was satisfied with the Weller $17,000 price. However, it had been pricing practice when loser prices were known to attempt to secure a lower overall price. This had happened with other contractors.

The Negotiation Memorandum also showed concessions by both parties. Each had altered its position several times on target cost, profit, share-ratio, and ceiling price. As finally negotiated, Hub's target cost had been reduced from $12,859 to $9,735, and there had been adjustments of profit percentages from the original position of each party. As they finally were incorporated in the contract, target costs had been arrived at on a total cost approach.

When Mr. Peterson, Hub's President, met with the contracting officer to discuss the price reduction, he was aware of Clause 51 of his contract, providing for a price reduction when a contract has: ". . . furnished incomplete or inaccurate cost or pricing data or data not current as certified in the contractor's Certificate of Current Cost or Pricing Data . . ." On the other hand, he was convinced that his firm had not violated either the letter, or the spirit of PL 87-653. After an exchange of greetings, Mr. Peterson introduced Mr. Blackstone, his attorney, to Mr. Brosky. The counselor was quick to "get down to the case at hand" presenting to the contracting officer the company's position that:

Hub does not object to the minor adjustments or the method of adjusting the contract amount, i.e., reducing the contract price by the target cost and target profit attributable to a nondisclosure. Hub objects to any adjustment being made and on the theory , that in the total cost negotiations in this case, the target cost would have been reduced by the entire amount of the difference between the Steele and Weller quotations .

Hub contends that no price adjustment is due because of its failure to disclose Steele's $15,451 price, quoted in June 19XO. Because that quotation was neither solicited nor received until after the 7 May 19XO date of certificate of current pricing and until after the prime contract price had been negotiated.

Hub further objects on various grounds to the government's entitlement to adjustments, as included in Mr. Brosky' s decision, contending:

Steele's quotation of 1 February 19XO was not cost or pricing data as of 7 May 19XO because it was conditioned on an unacceptable delivery schedule, had a 30-day acceptance limitation, and was at that time neither responsive nor current.

The quotation was in fact disclosed to the government prior to or in connection with the contract price negotiations.

If there was a nondisclosure, the government has failed to prove that it caused an overstatement in the contract price. That is, the government did not rely on Weller's $17,000 quotation or on the alleged absence of the Steele quotation. In addition to other evidence, the government's conduct in asserting no such claim when chargeable with knowledge of the facts shows its lack of reliance, its construction of the contract and, perhaps, a waiver of the right to a price adjustment.

QUESTIONS:

Evaluate each of Huh 's contentions. Do you agree or disagree? Why?

What should Mr. Brosky do now?

Cost Accounting, Accounting

  • Category:- Cost Accounting
  • Reference No.:- M92498012
  • Price:- $15

Priced at Now at $15, Verified Solution

Have any Question?


Related Questions in Cost Accounting

Assessment taskselect two public limited companies listed

Assessment task Select two public limited companies listed on the Australian Securities Exchange (ASX) that are in the same industry. Go to the website of your selected companies. Then go to the Investor Relations sectio ...

Research and write a paper on the topicthe ethics of

Research and write a paper on the Topic: The Ethics of manipulating budgets The paper should be approximately 3-4 double spaced written pages, plus your reference page (at least four references required) and any appendic ...

Assignment1 based on your topic given by your lecturer

Assignment: 1. Based on your topic given by your Lecturer, select two research-based journal articles relating to your topic. The articles you choose must cover a contemporary issue that is relevant to your topic. The jo ...

Assessment taskselect two public limited companies listed

Assessment task Select two public limited companies listed on the Australian Securities Exchange (ASX) that are in the same industry. Go to the website of your selected companies. Then go to the Investor Relations sectio ...

The balanced scorecard can be described as a tool that

The Balanced Scorecard can be described as a tool that "translates an organisation's mission and strategy into a set of performance measures that provide the framework for implementing its strategy" (Horgren et al., 2014 ...

Assignment - the effect of customer service experience on

Assignment - The Effect of Customer Service Experience on Subsequent Purchase Decisions One of our core topics this term will be to examine how management decisions affect sales volume and, therefore, company profits. Tw ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As