A company has been awarded a contract to build a house.  It is a contract Number 45 for the company and the contract price is shs.2.65 million. At the ending of the company's financial year, the contract was 85 percent complete and hence considered as being near completion. You are provided also along with the given information about the contract as:

Particulars

Shs.

Materials purchased and delivered

580,000

Materials issued from store

60,000

Materials returned to stores

7,000

Site expenses

300,000

Site wages                                           

200,000

Plant sent to site                                 

100,000

Architect's fees                                     

30,000

Plant returned from site                      

10,000

Subcontractor's fees               

105,000

Head Office overheads absorbed

  60,000

Valuation at the ending year disclosed the given as:

 

Shs

Materials:

19,500

Plant on site

50,000

Work done but not yet certified

60,000

Additional Information

1. The portion of the work that was completed throughout the year and certified via the architect was assessed as representing 75 percent of the whole contract price. The contractee made payments to this extent less 10 percent retention money.

2. The management of the company decided for the reasons of preparing the company's annual accounts to make a provision of a third of the national profit against the possibility of defects and other contingencies arising later in respect of the work already in previous certified for payment.

 Required 

a) The contract account 

b) Amount of loss or profit to be taken to the main loss and profit account of the company. 

c) Value of work in progress.

Contract No 45 Account

 

Shs

 

Shs

Materials Purchased:

580 ,000

Materials Returned to stores

9,000

Materials issued from stores

6,000

Plants returned from site

10,000

Site expenses

300,000

Materials c/f

19,500

Site wages

200,000

Plant c/f

50,000

Plant set to site

100,000

Cost of work done

1,346,500

Architects fees

30,000

 

 

Sub-contractors

105,000

 

 

Head office overheads

__60,000

 

     _______

 

1,435,500

 

1,435,500

Cost of work done b/d

1,346,500

Value of work certified

 

National profit:  701,000

 

75% x 2,650,000

1,987,500

Profit taken:

473,175

Work done but not

 

Profit in suspense

227,825

certified (closing stock)

___60,000

Balances b/f:  materials

19,500

 

2,047,500*

                       Plant

50,000     

 

 

                   Work not certified

60,000

 

 

Profit considered as:

= National Profit x (Cash Received /Contract Price)

= 701, 000 x (90 percent x 1, 987500) / 2,650,000

= 701, 000 x (1,788,750/ 265,000)

= 437, 175

Profit in Suspense   = 701,000 -473,175

                             =   Shs. 227,825

Value of Work in Progress:

 

Shs.

Cost of work certified

1,346,500

Add:  Profit taken

   473,175

 

1,819,675

Less:  Cash Received

(1,788,750)

Work in progress valuation:

     30,925

Cost Accounting, Accounting

  • Category:- Cost Accounting
  • Reference No.:- M9521151

Have any Question?


Related Questions in Cost Accounting

Assessment taskselect two public limited companies listed

Assessment task Select two public limited companies listed on the Australian Securities Exchange (ASX) that are in the same industry. Go to the website of your selected companies. Then go to the Investor Relations sectio ...

Assignment - the effect of customer service experience on

Assignment - The Effect of Customer Service Experience on Subsequent Purchase Decisions One of our core topics this term will be to examine how management decisions affect sales volume and, therefore, company profits. Tw ...

Research and write a paper on the topicthe ethics of

Research and write a paper on the Topic: The Ethics of manipulating budgets The paper should be approximately 3-4 double spaced written pages, plus your reference page (at least four references required) and any appendic ...

The balanced scorecard can be described as a tool that

The Balanced Scorecard can be described as a tool that "translates an organisation's mission and strategy into a set of performance measures that provide the framework for implementing its strategy" (Horgren et al., 2014 ...

Assessment taskselect two public limited companies listed

Assessment task Select two public limited companies listed on the Australian Securities Exchange (ASX) that are in the same industry. Go to the website of your selected companies. Then go to the Investor Relations sectio ...

Assignment1 based on your topic given by your lecturer

Assignment: 1. Based on your topic given by your Lecturer, select two research-based journal articles relating to your topic. The articles you choose must cover a contemporary issue that is relevant to your topic. The jo ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As