Ce 3361  project management                                                                        -1-

Project ivspring 2016: due 3 may 2016

Show all work and be neat

1. Illustrate the project manager contract model typically used in major construction activities such as power plants.

2. What are three principal duties of an inspector on a building project?

3. Who has responsibility when all the trees at the site die when there a no provisions in the contract for watering the trees during a dry period?

4. List at least three basic elements needed on all contract Drawings?

5. Is it ethical to take company pencils and paper home for your children to use at school because your employer did not Pay you overtime for your work on the weekends? 

6. In the bidding stage, what procedures do you follow when a Prospective contractor calls your office asking to Substitute a different type pipe than specified in the contract? 

7. At what stage in the project should the cost and schedule estimate be performed?

8. What are the responsibilities of the owner as a party to a construction contract?

9. Who has design responsibility for making changes in the  contract?

10. Your engineering firm has been contracted to solve a sewer Leak in a clay tile pipe next to the lucky lady horse Barn.  Your recommendation is to remove the existing Sewer and replace the entire 300-ft long section with a new 6-in.diameter pvcpipe.  Your design requires a 5-ft wide by 6.7 ft deep excavation with vertical side walls(see fig. 1 in Moodle).

A. You call dr. Mahar for his advise and he gives you the following list of activities and the activity sequence:

-          Replace asphalt                           - place/compact granular

                                                                       base course

-          Layout sewer line                        - excavate asphalt and     

Soil and remove

                                                                            damage pipe

-          Compact soil beneath                - place new 6 in. Pvc pipe

   new pvc pipe

-          Backfill and compact                - pavement markings

    trench

B. The activity sequence for replacing the damagedsewer

Line is given as follows:

11. prepare a quantity take off for each activity -fill in Following table.

    Item

activity

unit

estimated quantity

 

1

layout

 

 

 

2

 

 

 

 

3

 

 

 

 

4

place pipe

 

 

 

5

 

 

 

 

6

base course  

cy

 

 

7

 

 

 

 

8

lf

 

100

 

Ac  - acres:  1 ft2  =   0.00002296 acres

Cy  - cubic yards: 27 ft3/cy

Lf  - linear feet

Sy - square yards: 9 ft2/sy

Fig. 1 excavation cross-section (separate page in moodle)

12. Prepare an engineer cost estimate for performing the sewer Replacement work (means estimating sheets on moodle).

   item

activity

Unit estimated

unit price quantity

total cost

 

 

 

 

 

1

 

 

 

 

2

excavate

cy 

 

 

3

 

 

 

 

4

 

 

 

 

5

 

 

 

 

6

 

cy 

 

 

7

 

 

 

 

8

markings

lf 

 

100

13. Prepare an engineer schedule estimate for performing the Sewerreplacement work (means estimating sheets on moodle).

   item

activity

Unit production

quantity

daily

duration

 

 

 

 

 

 

1

 

 

 

 

 

2

excavate

cy 

 

 

 

3

 

 

 

 

 

4

 

 

 

 

 

5

 

 

 

 

 

6

 

cy 

 

 

 

7

 

 

 

 

 

8

markings

lf 

 


 

14. Prepare a bar chart schedule for managing the sewer Replacement work.(use a separate sheet of paper)

15. Identify 3 safety/environmental concerns. Do not forget the Snake fence.

Microeconomics, Economics

  • Category:- Microeconomics
  • Reference No.:- M91773188
  • Price:- $35

Priced at Now at $35, Verified Solution

Have any Question?


Related Questions in Microeconomics

Question show the market for cigarettes in equilibrium

Question: Show the market for cigarettes in equilibrium, assuming that there are no laws banning smoking in public. Label the equilibrium private market price and quantity as Pm and Qm. Add whatever is needed to the mode ...

Question recycling is a relatively inexpensive solution to

Question: Recycling is a relatively inexpensive solution to much of the environmental contamination from plastics, glass, and other waste materials. Is it a sound policy to make it mandatory for everybody to recycle? The ...

Question consider two ways of protecting elephants from

Question: Consider two ways of protecting elephants from poachers in African countries. In one approach, the government sets up enormous national parks that have sufficient habitat for elephants to thrive and forbids all ...

Question suppose you want to put a dollar value on the

Question: Suppose you want to put a dollar value on the external costs of carbon emissions from a power plant. What information or data would you obtain to measure the external [not social] cost? The response must be typ ...

Question in the tradeoff between economic output and

Question: In the tradeoff between economic output and environmental protection, what do the combinations on the protection possibility curve represent? The response must be typed, single spaced, must be in times new roma ...

Question consider the case of global environmental problems

Question: Consider the case of global environmental problems that spill across international borders as a prisoner's dilemma of the sort studied in Monopolistic Competition and Oligopoly. Say that there are two countries ...

Question consider two approaches to reducing emissions of

Question: Consider two approaches to reducing emissions of CO2 into the environment from manufacturing industries in the United States. In the first approach, the U.S. government makes it a policy to use only predetermin ...

Question the state of colorado requires oil and gas

Question: The state of Colorado requires oil and gas companies who use fracking techniques to return the land to its original condition after the oil and gas extractions. Table 12.9 shows the total cost and total benefit ...

Question suppose a city releases 16 million gallons of raw

Question: Suppose a city releases 16 million gallons of raw sewage into a nearby lake. Table shows the total costs of cleaning up the sewage to different levels, together with the total benefits of doing so. (Benefits in ...

Question four firms called elm maple oak and cherry produce

Question: Four firms called Elm, Maple, Oak, and Cherry, produce wooden chairs. However, they also produce a great deal of garbage (a mixture of glue, varnish, sandpaper, and wood scraps). The first row of Table 12.6 sho ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As